Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2008 |
Principal Product | Newspaper Printing Plates |
NAICS | 323120 - Support Activities for Printing |
SIC | 2672 - Paper Coated And Laminated, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 185,000 |
Annual Production | 6,000,000 Pieces |
Production Hrs. Annual | 7,200 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $366,374 | 4,526,567 | kWh | $0.08 |
Electricity Demand | $191,931 | 29,952 | kW-months/year | $6.41 |
Electricity Fees | $66,701 | - | $ | - |
Natural Gas | $222,747 | 25,832 | MMBtu | $8.62 |
TOTAL ENERGY COSTS | $847,753 | |||
RECOMMENDED SAVINGS* | $226,344 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $217,227 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $117,665 Cost: $1,117,600 |
$78,590 | 3,474,720 | $39,075 | 6,096 | - | - |
$78,590 3,474,720 kWh |
$39,075 6,096 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.5111 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS |
Savings: $62,965 Cost: $69,500 |
- | - | - | - | $62,965 | 7,310 |
- - kWh |
- - kW-months/year |
$62,965 7,310 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $16,824 Cost: $22,665 |
$14,850 | 183,561 | $1,974 | 308 | - | - |
$14,850 183,561 kWh |
$1,974 308 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $11,507 Cost: $900 |
$10,165 | 125,651 | $1,342 | 209 | - | - |
$10,165 125,651 kWh |
$1,342 209 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $7,660 Cost: $4,270 |
- | - | - | - | $7,660 | 889 |
- - kWh |
- - kW-months/year |
$7,660 889 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,270 Cost: $4,650 |
$5,270 | 65,152 | - | - | - | - |
$5,270 65,152 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,436 Cost: $3,324 |
$2,436 | 30,112 | - | - | - | - |
$2,436 30,112 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,411 Cost: $3,110 |
$1,244 | 15,380 | $167 | 26 | - | - |
$1,244 15,380 kWh |
$167 26 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $606 Cost: $256 |
$606 | 7,349 | - | - | - | - |
$606 7,349 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $226,344 Cost: $1,226,275 |
$113,161 | 3,901,925 | $42,558 | 6,639 | $70,625 | 8,199 | $113,161 3,901,925 kWh |
$42,558 6,639 kW-months/year |
$70,625 8,199 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $217,227 Cost: $1,215,191 |
$104,211 | 3,791,281 | $42,391 | 6,613 | $70,625 | 8,199 | $104,211 3,791,281 kWh |
$42,391 6,613 kW-months/year |
$70,625 8,199 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |