IAC Assessment: SD0426
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2010
Principal Product plastic films and bags
NAICS 326111 - Plastics Bag and Pouch Manufacturing
SIC 3081 - Unsupported Plastics Film & Sheet
Sales $10,000,000-$50,000,000
# of Employees 40
Plant Area (Sq.Ft.) 50,000
Annual Production 17,000,000 Pounds
Production Hrs. Annual 6,120
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $289,886 3,627,390 kWh $0.08
Electricity Demand $158,625 10,839 kW-months/year $14.63
Electricity Fees $49,448 - $ -
TOTAL ENERGY COSTS $497,959
RECOMMENDED SAVINGS* $87,219 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $21,801
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,373
Cost:
$100
$2,373 29,697 - - $2,373
29,697
kWh
-
-
kW-months/year
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,943
Cost:
$1,000
$4,377 54,786 $1,566 107 $4,377
54,786
kWh
$1,566
107
kW-months/year
03: 2.7145 INSTALL SKYLIGHTS Savings:
$10,372
Cost:
$7,660
$10,372 95,555 - - $10,372
95,555
kWh
-
-
kW-months/year
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$33,632
Cost:
$94,584
$24,152 302,282 $9,480 648 $24,152
302,282
kWh
$9,480
648
kW-months/year
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$21,414
Cost:
$59,920
$15,357 192,207 $6,057 420 $15,357
192,207
kWh
$6,057
420
kW-months/year
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$13,485
Cost:
$54,987
$9,899 123,887 $3,586 245 $9,899
123,887
kWh
$3,586
245
kW-months/year
TOTAL RECOMMENDED Savings:
$87,219
Cost:
$218,251
$66,530 798,414 $20,689 1,420 $66,530
798,414
kWh
$20,689
1,420
kW-months/year
TOTAL IMPLEMENTED Savings:
$21,801
Cost:
$56,087
$16,649 208,370 $5,152 352 $16,649
208,370
kWh
$5,152
352
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand