IAC logo
IAC Assessment: SD0427
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0427
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2010
Principal Product CSD manufacture
NAICS 312111 - Soft Drink Manufacturing
SIC 2086 - Bottled And Canned Soft Drinks
Sales $50,000,000-$100,000,000
# of Employees 125
Plant Area (Sq.Ft.) 220,000
Annual Production 350 Units
Production Hrs. Annual 8,736
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $801,604 9,970,329 kWh $0.08
Electricity Demand $433,013 23,584 kW-months/year $18.36
Electricity Fees $113,509 - $ -
Natural Gas $100,903 15,826 MMBtu $6.38
TOTAL ENERGY COSTS $1,449,029
RECOMMENDED SAVINGS* $557,131 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,780
Cost:
$100
$1,780 22,147 - - $1,780
22,147
kWh
-
-
kW-months/year
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$8,494
Cost:
$2,714
$5,902 73,416 $2,592 141 $5,902
73,416
kWh
$2,592
141
kW-months/year
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$1,124
Cost:
$1,230
$1,124 13,976 - - $1,124
13,976
kWh
-
-
kW-months/year
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,450
Cost:
$10,035
$1,990 24,752 $2,460 134 $1,990
24,752
kWh
$2,460
134
kW-months/year
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$486
Cost:
$2,200
$486 6,043 - - $486
6,043
kWh
-
-
kW-months/year
06: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$540,797
Cost:
$1,949,400
$253,848 8,127,288 $286,949 15,629 $253,848
8,127,288
kWh
$286,949
15,629
kW-months/year
TOTAL RECOMMENDED Savings:
$557,131
Cost:
$1,965,679
$265,130 8,267,622 $292,001 15,904 $265,130
8,267,622
kWh
$292,001
15,904
kW-months/year
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand