Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2012 |
Principal Product | Treated Water |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4952 - Sewerage Systems |
Sales | $10,000,000-$50,000,000 |
# of Employees | 13 |
Plant Area (Sq.Ft.) | 2,560,000 |
Annual Production | 11,500 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,045,469 | 11,979,368 | kWh | $0.09 |
Electricity Demand | $388,588 | 25,575 | kW-months/year | $15.19 |
Electricity Fees | $11,590 | - | $ | - |
Natural Gas | $257,486 | 46,277 | MMBtu | $5.56 |
TOTAL ENERGY COSTS | $1,703,133 | |||
RECOMMENDED SAVINGS* | $187,969 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $177,897 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1336 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL |
Savings: $48,619 Cost: $2,000 |
- | - | - | - | $48,619 | 8,738 | - | - |
- - kWh |
- - kW-months/year |
$48,619 8,738 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $24,957 Cost: $15,925 |
$19,170 | 219,585 | $5,787 | 381 | - | - | - | - |
$19,170 219,585 kWh |
$5,787 381 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $10,072 Cost: $18,680 |
$8,128 | 93,104 | $1,944 | 128 | - | - | - | - |
$8,128 93,104 kWh |
$1,944 128 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $2,223 Cost: $4,200 |
- | - | - | - | $2,223 | 400 | - | - |
- - kWh |
- - kW-months/year |
$2,223 400 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $102,098 Cost: $275,000 |
$65,475 | 750,000 | $15,190 | 1,000 | $28,933 | 5,200 | $(-7,500) | - |
$65,475 750,000 kWh |
$15,190 1,000 kW-months/year |
$28,933 5,200 MMBtu |
$(-7,500) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $187,969 Cost: $315,805 |
$92,773 | 1,062,689 | $22,922 | 1,509 | $79,775 | 14,338 | $(-7,500) | - | $92,773 1,062,689 kWh |
$22,922 1,509 kW-months/year |
$79,775 14,338 MMBtu |
$(-7,500) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $177,897 Cost: $297,125 |
$84,645 | 969,585 | $20,977 | 1,381 | $79,775 | 14,338 | $(-7,500) | - | $84,645 969,585 kWh |
$20,977 1,381 kW-months/year |
$79,775 14,338 MMBtu |
$(-7,500) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |