IAC Assessment: SD0458
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0458
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2012
Principal Product Pork Products
NAICS 311611 - Animal (except Poultry) Slaughtering
SIC 2013 - Sausages And Other Prepared Meats
Sales $100,000,000-$500,000,000
# of Employees 643
Plant Area (Sq.Ft.) 450,000
Annual Production 740,000 Pounds
Production Hrs. Annual 6,240
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,447,947 18,764,159 kWh $0.08
Electricity Demand $737,449 55,593 kW-months/year $13.27
Electricity Fees $65,990 - $ -
Natural Gas $392,692 70,446 MMBtu $5.57
TOTAL ENERGY COSTS $2,644,078
RECOMMENDED SAVINGS* $392,678 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,667
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Electricity Usage Electricity Demand Natural Gas Water Disposal
$ kWh $ kW-months/year $ MMBtu $ Tgal
01: 2.5194 REDESIGN PROCESS Savings:
$272,976
Cost:
$164,279
$(-7,568) (-98,035) $(-1,782) (-134) $150,926 27,077 $131,400 29,200,000 $(-7,568)
(-98,035)
kWh
$(-1,782)
(-134)
kW-months/year
$150,926
27,077
MMBtu
$131,400
29,200,000
Tgal
02: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) Savings:
$46,732
Cost:
$123,300
- - - - $46,732 8,384 - - -
-
kWh
-
-
kW-months/year
$46,732
8,384
MMBtu
-
-
Tgal
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$29,502
Cost:
$58,740
$25,377 328,718 $4,125 311 - - - - $25,377
328,718
kWh
$4,125
311
kW-months/year
-
-
MMBtu
-
-
Tgal
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$22,833
Cost:
$11,000
- - - - $22,833 4,096 - - -
-
kWh
-
-
kW-months/year
$22,833
4,096
MMBtu
-
-
Tgal
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,667
Cost:
$34,450
$8,768 113,579 $2,899 219 - - - - $8,768
113,579
kWh
$2,899
219
kW-months/year
-
-
MMBtu
-
-
Tgal
06: 2.2511 INSULATE BARE EQUIPMENT Savings:
$7,861
Cost:
$8,422
- - - - $7,861 1,410 - - -
-
kWh
-
-
kW-months/year
$7,861
1,410
MMBtu
-
-
Tgal
07: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE Savings:
$1,107
Cost:
$200
- - - - $1,107 199 - - -
-
kWh
-
-
kW-months/year
$1,107
199
MMBtu
-
-
Tgal
TOTAL RECOMMENDED Savings:
$392,678
Cost:
$400,391
$26,577 344,262 $5,242 395 $229,459 41,166 $131,400 29,200,000 $26,577
344,262
kWh
$5,242
395
kW-months/year
$229,459
41,166
MMBtu
$131,400
29,200,000
Tgal
TOTAL IMPLEMENTED Savings:
$11,667
Cost:
$34,450
$8,768 113,579 $2,899 219 - - - - $8,768
113,579
kWh
$2,899
219
kW-months/year
-
-
MMBtu
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal
Electricity Usage Electricity Demand Natural Gas Water Disposal Electricity Usage Electricity Demand Natural Gas Water Disposal