Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2023 |
Principal Product | Precision Machining (CNC) Services |
NAICS | 332710 - Machine Shops |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 38 |
Plant Area (Sq.Ft.) | 12,800 |
Annual Production | 140,000 Units |
Production Hrs. Annual | 4,080 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $53,531 | 480,777 | kWh | $0.11 |
Electricity Demand | $41,837 | 1,218 | kW-months/year | $34.35 |
Electricity Fees | $14,954 | - | $ | - |
TOTAL ENERGY COSTS | $128,322 | |||
RECOMMENDED SAVINGS* | $78,597 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $78,597 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.8113 PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) |
Savings: $11,699 Cost: $6,300 |
- | - | - | - | $11,699 | 495 | - | - |
- - kWh |
- - kW-months/year |
$11,699 495 gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $49,059 Cost: $77,697 |
$21,854 | 196,350 | $27,205 | 792 | - | - | - | - |
$21,854 196,350 kWh |
$27,205 792 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4223 INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM |
Savings: $4,401 Cost: $6,200 |
$4,401 | 39,546 | - | - | - | - | - | - |
$4,401 39,546 kWh |
- - kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,191 Cost: $8,424 |
$1,044 | 9,381 | $1,131 | 33 | - | - | $16 | - |
$1,044 9,381 kWh |
$1,131 33 kW-months/year |
- - gal |
$16 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $440 Cost: $570 |
$255 | 2,295 | $185 | 5 | - | - | - | - |
$255 2,295 kWh |
$185 5 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $641 Cost: $1,749 |
$366 | 3,290 | $275 | 8 | - | - | - | - |
$366 3,290 kWh |
$275 8 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3141 USE BATTERY STORAGE FOR DEMAND CONTROL |
Savings: $9,071 Cost: $1,121 |
$(-2,573) | (-23,112) | $11,644 | 339 | - | - | - | - |
$(-2,573) (-23,112) kWh |
$11,644 339 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,095 Cost: $3,366 |
$635 | 5,707 | $460 | 13 | - | - | - | - |
$635 5,707 kWh |
$460 13 kW-months/year |
- - gal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $78,597 Cost: $105,427 |
$25,982 | 233,457 | $40,900 | 1,191 | $11,699 | 495 | $16 | - | $25,982 233,457 kWh |
$40,900 1,191 kW-months/year |
$11,699 495 gal |
$16 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $78,597 Cost: $105,427 |
$25,982 | 233,457 | $40,900 | 1,191 | $11,699 | 495 | $16 | - | $25,982 233,457 kWh |
$40,900 1,191 kW-months/year |
$11,699 495 gal |
$16 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes |