IAC Assessment: SF0050
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0050
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 1995
Principal Product Corrugated Cartons
NAICS n/a
SIC 2653 - Corrugated And Solid Fiber Boxes
Sales $50,000,000-$100,000,000
# of Employees 190
Plant Area (Sq.Ft.) 435,600
Annual Production 100,000 Tons
Production Hrs. Annual 7,238
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $765,297 8,568,582 kWh $0.09
Natural Gas $299,594 96,611 MMBtu $3.10
TOTAL ENERGY COSTS $1,064,891
RECOMMENDED SAVINGS* $565,986 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $56,203
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$48,642
Cost:
$166,900
$48,642 544,549 - - $48,642
544,549
kWh
-
-
MMBtu
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$3,578
Cost:
$5,911
$3,578 - - - $3,578
-
kWh
-
-
MMBtu
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$2,230
Cost:
$1,125
$2,230 24,912 - - $2,230
24,912
kWh
-
-
MMBtu
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$21,960
Cost:
$19,510
$21,960 245,897 - - $21,960
245,897
kWh
-
-
MMBtu
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,254
Cost:
$748
- - $1,254 409 -
-
kWh
$1,254
409
MMBtu
06: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$401
Cost:
$81
- - $401 129 -
-
kWh
$401
129
MMBtu
07: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER Savings:
$4,773
Cost:
$25,000
- - $4,773 1,526 -
-
kWh
$4,773
1,526
MMBtu
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,930
Cost:
$900
- - $4,930 188 -
-
kWh
$4,930
188
MMBtu
09: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$478,218
Cost:
$653,645
$707,157 7,962,192 $(-228,939) (-73,828) $707,157
7,962,192
kWh
$(-228,939)
(-73,828)
MMBtu
TOTAL RECOMMENDED Savings:
$565,986
Cost:
$873,820
$783,567 8,777,550 $(-217,581) (-71,576) $783,567
8,777,550
kWh
$(-217,581)
(-71,576)
MMBtu
TOTAL IMPLEMENTED Savings:
$56,203
Cost:
$169,006
$50,872 569,461 $5,331 317 $50,872
569,461
kWh
$5,331
317
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas