Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 1995 |
Principal Product | Processed Eggs |
NAICS | n/a |
SIC | 2099 - Food Preparations, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 35,000 |
Annual Production | 450,000 Units |
Production Hrs. Annual | 2,500 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $303,814 | 3,539,273 | kWh | $0.09 |
Natural Gas | $93,309 | 16,311 | MMBtu | $5.72 |
TOTAL ENERGY COSTS | $397,123 | |||
RECOMMENDED SAVINGS* | $82,913 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,563 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $390 Cost: $1,548 |
$390 | 4,396 | - | - |
$390 4,396 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $826 Cost: $2,750 |
$826 | 9,672 | - | - |
$826 9,672 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,925 Cost: $13,715 |
$5,925 | 68,875 | - | - |
$5,925 68,875 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $808 Cost: $1,116 |
$808 | 9,379 | - | - |
$808 9,379 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $830 Cost: $1,650 |
$1,159 | 13,482 | $(-329) | (-58) |
$1,159 13,482 kWh |
$(-329) (-58) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,861 Cost: $5,341 |
$2,861 | - | - | - |
$2,861 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $71,273 Cost: $230,000 |
$157,451 | 1,845,252 | $(-86,178) | (-15,066) |
$157,451 1,845,252 kWh |
$(-86,178) (-15,066) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $82,913 Cost: $256,120 |
$169,420 | 1,951,056 | $(-86,507) | (-15,124) | $169,420 1,951,056 kWh |
$(-86,507) (-15,124) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,563 Cost: $16,481 |
$7,892 | 91,736 | $(-329) | (-58) | $7,892 91,736 kWh |
$(-329) (-58) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |