Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 1997 |
Principal Product | Injection Molding Parts |
NAICS | n/a |
SIC | 3085 - Plastics Bottles |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 5,000,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $131,382 | 1,474,795 | kWh | $0.09 |
Electricity Demand | $21,249 | 5,124 | kW-months/year | $4.15 |
Natural Gas | $5,239 | 734 | MMBtu | $7.14 |
TOTAL ENERGY COSTS | $166,963 | |||
RECOMMENDED SAVINGS* | $27,047 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,019 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $119 Cost: $11,984 |
$23 | 7,327 | $96 | 699 | - | - | - | - |
$23 7,327 kWh |
$96 699 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,990 Cost: $16,568 |
$5,521 | 61,841 | $1,469 | 354 | - | - | - | - |
$5,521 61,841 kWh |
$1,469 354 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $435 Cost: $360 |
$343 | 3,810 | $92 | 22 | - | - | - | - |
$343 3,810 kWh |
$92 22 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $1,601 Cost: $7,400 |
$1,262 | 14,068 | $339 | 82 | - | - | - | - |
$1,262 14,068 kWh |
$339 82 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,713 Cost: - |
$2,490 | 27,843 | $223 | 54 | - | - | - | - |
$2,490 27,843 kWh |
$223 54 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,365 Cost: $3,180 |
$905 | 10,258 | $460 | 111 | - | - | - | - |
$905 10,258 kWh |
$460 111 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,395 Cost: - |
$3,116 | 34,877 | $279 | 67 | - | - | - | - |
$3,116 34,877 kWh |
$279 67 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $766 Cost: $2,301 |
$766 | 8,499 | - | - | - | - | - | - |
$766 8,499 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.1121 USE MORE EFFICIENT ADHESIVE APPLICATORS |
Savings: $7,120 Cost: $5,285 |
- | - | - | - | $4,680 | 99,840 | $2,440 | - |
- - kWh |
- - kW-months/year |
$4,680 99,840 lb |
$2,440 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $2,543 Cost: $1,200 |
- | - | - | - | - | - | $2,543 | - |
- - kWh |
- - kW-months/year |
- - lb |
$2,543 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $27,047 Cost: $48,278 |
$14,426 | 168,523 | $2,958 | 1,389 | $4,680 | 99,840 | $4,983 | - | $14,426 168,523 kWh |
$2,958 1,389 kW-months/year |
$4,680 99,840 lb |
$4,983 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,019 Cost: $38,613 |
$13,521 | 158,265 | $2,498 | 1,278 | - | - | - | - | $13,521 158,265 kWh |
$2,498 1,278 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes |