IAC logo
IAC Assessment: SF0165
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0165
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 1999
Principal Product Injection Molded Plastic Parts
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 50
Plant Area (Sq.Ft.) 25,000
Annual Production 1,000,000 Pounds
Production Hrs. Annual 6,240
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $89,811 1,503,224 kWh $0.06
Electricity Demand $42,460 3,886 kW-months/year $10.93
Natural Gas $1,830 238 MMBtu $7.69
TOTAL ENERGY COSTS $141,892
RECOMMENDED SAVINGS* $51,237 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes
$ kWh $ kW-months/year $ lb $ $
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$535
Cost:
$889
$395 6,741 $140 13 - - - - $395
6,741
kWh
$140
13
kW-months/year
-
-
lb
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$7,152
Cost:
$14,840
$5,043 84,408 $2,109 193 - - - - $5,043
84,408
kWh
$2,109
193
kW-months/year
-
-
lb
-
-
$
03: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE Savings:
$491
Cost:
$1,250
$239 4,103 $252 23 - - - - $239
4,103
kWh
$252
23
kW-months/year
-
-
lb
-
-
$
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$12,333
Cost:
$51,850
$9,623 161,196 $2,710 248 - - - - $9,623
161,196
kWh
$2,710
248
kW-months/year
-
-
lb
-
-
$
05: 3.5314 USE IN-PROCESS RECYCLING WHENEVER POSSIBLE Savings:
$726
Cost:
-
- - - - $726 - - - -
-
kWh
-
-
kW-months/year
$726
-
lb
-
-
$
06: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$30,000
Cost:
$2,773
- - - - - - $30,000 - -
-
kWh
-
-
kW-months/year
-
-
lb
$30,000
-
$
TOTAL RECOMMENDED Savings:
$51,237
Cost:
$71,602
$15,300 256,448 $5,211 477 $726 - $30,000 - $15,300
256,448
kWh
$5,211
477
kW-months/year
$726
-
lb
$30,000
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Administrative Changes