IAC Assessment: SF0322
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0322
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2006
Principal Product Asphalt
NAICS 324121 - Asphalt Paving Mixture and Block Manufacturing
SIC 2951 - Asphalt Paving Mixtures And Blocks
Sales $5,000,000-$10,000,000
# of Employees 11
Plant Area (Sq.Ft.) 163,350
Annual Production 300,000 Tons
Production Hrs. Annual 1,680
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $161,347 1,586,603 kWh $0.10
Electricity Demand $122,556 9,897 kW-months/year $12.38
Natural Gas $784,681 118,420 MMBtu $6.63
TOTAL ENERGY COSTS $1,068,584
RECOMMENDED SAVINGS* $28,408 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $27,371
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$7,560
Cost:
$660
- - - - $7,560 1,240 -
-
kWh
-
-
kW-months/year
$7,560
1,240
MMBtu
02: 2.2511 INSULATE BARE EQUIPMENT Savings:
$19,058
Cost:
$11,866
- - - - $19,058 2,874 -
-
kWh
-
-
kW-months/year
$19,058
2,874
MMBtu
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$31
Cost:
$29,800
$31 - - - - - $31
-
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$462
Cost:
$2,393
$1 14 $461 107 - - $1
14
kWh
$461
107
kW-months/year
-
-
MMBtu
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1
Cost:
$1,698
- - - - $1 249 -
-
kWh
-
-
kW-months/year
$1
249
MMBtu
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$19
Cost:
$24,854
$10 106 $9 760 - - $10
106
kWh
$9
760
kW-months/year
-
-
MMBtu
07: 2.7134 USE PHOTOCELL CONTROLS Savings:
$237
Cost:
$345
$113 1 $124 10 - - $113
1
kWh
$124
10
kW-months/year
-
-
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$509
Cost:
$1,320
$364 3 $145 11 - - $364
3
kWh
$145
11
kW-months/year
-
-
MMBtu
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4
Cost:
$15,259
$2 25 $2 180 - - $2
25
kWh
$2
180
kW-months/year
-
-
MMBtu
10: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$527
Cost:
$1,445
$255 2 $272 21 - - $255
2
kWh
$272
21
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$28,408
Cost:
$89,640
$776 151 $1,013 1,089 $26,619 4,363 $776
151
kWh
$1,013
1,089
kW-months/year
$26,619
4,363
MMBtu
TOTAL IMPLEMENTED Savings:
$27,371
Cost:
$85,177
$157 146 $596 1,057 $26,618 4,114 $157
146
kWh
$596
1,057
kW-months/year
$26,618
4,114
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas