Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2015 |
Principal Product | Construction Materials |
NAICS | 212313 - Crushed and Broken Granite Mining and Quarrying |
SIC | 1423 - Crushed And Broken Granite |
Sales | $100,000,000-$500,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 11,600,000 |
Annual Production | 4,000,000 Tons |
Production Hrs. Annual | 2,640 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $734,696 | 13,840,967 | kWh | $0.05 |
Electricity Demand | $0 | 78,191 | kW-months/year | $0.00 |
Natural Gas | $538,122 | 84,082 | MMBtu | $6.40 |
TOTAL ENERGY COSTS | $1,272,818 | |||
RECOMMENDED SAVINGS* | $59,359 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,437 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Primary Raw Material | Electricity Usage | Natural Gas | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $3,119 Cost: - |
$3,119 | 58,757 | - | - | - | - | - | - |
$3,119 58,757 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,437 Cost: - |
$2,437 | 45,927 | - | - | - | - | - | - |
$2,437 45,927 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $12,922 Cost: $8,500 |
- | - | $12,922 | 2,019 | - | - | - | - |
- - kWh |
$12,922 2,019 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $6,324 Cost: $4,543 |
$6,324 | 119,145 | - | - | - | - | - | - |
$6,324 119,145 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,388 Cost: $5,977 |
$1,388 | 26,155 | - | - | - | - | - | - |
$1,388 26,155 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $522 Cost: $2,846 |
$522 | 9,835 | - | - | - | - | - | - |
$522 9,835 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $32,647 Cost: $223,755 |
$35,673 | 672,053 | - | - | $3,631 | - | $(-6,657) | - |
$35,673 672,053 kWh |
- - MMBtu |
$3,631 - $ |
$(-6,657) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $59,359 Cost: $245,621 |
$49,463 | 931,872 | $12,922 | 2,019 | $3,631 | - | $(-6,657) | - | $49,463 931,872 kWh |
$12,922 2,019 MMBtu |
$3,631 - $ |
$(-6,657) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,437 Cost: $237,121 |
$49,463 | 931,872 | - | - | $3,631 | - | $(-6,657) | - | $49,463 931,872 kWh |
- - MMBtu |
$3,631 - $ |
$(-6,657) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Primary Raw Material | Electricity Usage | Natural Gas | Administrative Changes | Primary Raw Material |