IAC Assessment: SF0470
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0470
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2015
Principal Product bread and muffins
NAICS 311812 - Commercial Bakeries
SIC 2051 - Bread, Cake, And Related Products
Sales $10,000,000-$50,000,000
# of Employees 130
Plant Area (Sq.Ft.) 86,679
Annual Production 70,000,000 Pounds
Production Hrs. Annual 7,488
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $552,779 5,947,277 kWh $0.09
Electricity Demand $310,391 11,480 kW-months/year $27.04
Natural Gas $362,933 53,424 MMBtu $6.79
TOTAL ENERGY COSTS $1,226,103
RECOMMENDED SAVINGS* $143,132 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $143,132
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Water Consumption Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Water Consumption
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ Tgal
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$10,220
Cost:
$4,488
$7,083 76,198 $3,137 116 - - - - - - - - $7,083
76,198
kWh
$3,137
116
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
Tgal
02: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$5,421
Cost:
$3,541
$5,421 58,318 - - - - - - - - - - $5,421
58,318
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
Tgal
03: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED Savings:
$26,563
Cost:
$30,811
- - - - $14,293 2,099 - - - - $12,270 - -
-
kWh
-
-
kW-months/year
$14,293
2,099
MMBtu
-
-
$
-
-
$
$12,270
-
Tgal
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$5,546
Cost:
$11,844
- - - - $5,546 816 - - - - - - -
-
kWh
-
-
kW-months/year
$5,546
816
MMBtu
-
-
$
-
-
$
-
-
Tgal
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,206
Cost:
$17,797
$3,834 41,246 - - - - $598 - $(-226) - - - $3,834
41,246
kWh
-
-
kW-months/year
-
-
MMBtu
$598
-
$
$(-226)
-
$
-
-
Tgal
06: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$91,176
Cost:
$450,224
$52,052 559,997 $39,124 1,447 - - - - - - - - $52,052
559,997
kWh
$39,124
1,447
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
Tgal
TOTAL RECOMMENDED Savings:
$143,132
Cost:
$518,705
$68,390 735,759 $42,261 1,563 $19,839 2,915 $598 - $(-226) - $12,270 - $68,390
735,759
kWh
$42,261
1,563
kW-months/year
$19,839
2,915
MMBtu
$598
-
$
$(-226)
-
$
$12,270
-
Tgal
TOTAL IMPLEMENTED Savings:
$143,132
Cost:
$518,705
$68,390 735,759 $42,261 1,563 $19,839 2,915 $598 - $(-226) - $12,270 - $68,390
735,759
kWh
$42,261
1,563
kW-months/year
$19,839
2,915
MMBtu
$598
-
$
$(-226)
-
$
$12,270
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ Tgal
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Water Consumption Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Water Consumption