IAC Assessment: SF0509
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0509
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2017
Principal Product Wine
NAICS 312130 - Wineries
SIC 2084 - Wines, Brandy, And Brandy Spirits
Sales $100,000,000-$500,000,000
# of Employees 91
Plant Area (Sq.Ft.) 276,287
Annual Production 6,000 Thousand Gallons
Production Hrs. Annual 3,480
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $371,192 3,511,307 kWh $0.11
Electricity Demand $179,755 5,832 kW-months/year $30.82
Natural Gas $46,574 4,654 MMBtu $10.01
TOTAL ENERGY COSTS $597,521
RECOMMENDED SAVINGS* $136,581 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $80,854
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.7496 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE Savings:
$2,452
Cost:
-
$1,492 14,115 - - $960 96 - - - - $1,492
14,115
kWh
-
-
kW-months/year
$960
96
MMBtu
-
-
$
-
-
$
02: 2.5195 CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS Savings:
$6,821
Cost:
-
$6,821 64,522 - - - - - - - - $6,821
64,522
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$17,732
Cost:
$2,539
$3,514 33,246 - - $14,218 1,420 - - - - $3,514
33,246
kWh
-
-
kW-months/year
$14,218
1,420
MMBtu
-
-
$
-
-
$
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$596
Cost:
$140
$249 2,354 $347 11 - - - - - - $249
2,354
kWh
$347
11
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$11,813
Cost:
$10,550
$11,813 99,374 - - - - - - - - $11,813
99,374
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$38,416
Cost:
$53,848
$18,520 175,200 $15,019 492 - - $5,259 - $(-382) - $18,520
175,200
kWh
$15,019
492
kW-months/year
-
-
MMBtu
$5,259
-
$
$(-382)
-
$
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$12,893
Cost:
$42,428
$12,893 121,962 - - - - - - - - $12,893
121,962
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$7,625
Cost:
$31,216
$6,204 58,689 $3,233 105 $(-1,812) (-181) - - - - $6,204
58,689
kWh
$3,233
105
kW-months/year
$(-1,812)
(-181)
MMBtu
-
-
$
-
-
$
09: 4.212 ADOPT IN-HOUSE MATERIAL GENERATION Savings:
$38,233
Cost:
$90,166
$(-3,898) (-36,874) $(-4,962) (-161) - - - - $47,093 - $(-3,898)
(-36,874)
kWh
$(-4,962)
(-161)
kW-months/year
-
-
MMBtu
-
-
$
$47,093
-
$
TOTAL RECOMMENDED Savings:
$136,581
Cost:
$230,887
$57,608 532,588 $13,637 448 $13,366 1,335 $5,259 - $46,711 - $57,608
532,588
kWh
$13,637
448
kW-months/year
$13,366
1,335
MMBtu
$5,259
-
$
$46,711
-
$
TOTAL IMPLEMENTED Savings:
$80,854
Cost:
$109,365
$46,740 429,782 $15,019 492 $14,218 1,420 $5,259 - $(-382) - $46,740
429,782
kWh
$15,019
492
kW-months/year
$14,218
1,420
MMBtu
$5,259
-
$
$(-382)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost