IAC Assessment: SF0517
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0517
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2018
Principal Product Treated Wastewater
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales $1,000,000-$5,000,000
# of Employees 14
Plant Area (Sq.Ft.) 13,372,920
Annual Production 1,328,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $131,015 787,512 kWh $0.17
Natural Gas $19,663 1,710 MMBtu $11.50
TOTAL ENERGY COSTS $150,678
RECOMMENDED SAVINGS* $278,388 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $278,104
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Administrative Changes Electricity Usage Natural Gas Personnel Changes Administrative Changes
$ kWh $ MMBtu $ $ $ $
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$7,086
Cost:
$200
$7,086 42,595 - - - - - - $7,086
42,595
kWh
-
-
MMBtu
-
-
$
-
-
$
02: 2.4313 PROVIDE PROPER MAINTENANCE OF MOTOR DRIVEN EQUIPMENT Savings:
$284
Cost:
$100
$284 1,704 - - - - - - $284
1,704
kWh
-
-
MMBtu
-
-
$
-
-
$
03: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$1,563
Cost:
$803
- - $1,563 136 - - - - -
-
kWh
$1,563
136
MMBtu
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,262
Cost:
$6,590
$6,262 36,938 - - - - - - $6,262
36,938
kWh
-
-
MMBtu
-
-
$
-
-
$
05: 2.1336 INSTALL EQUIPMENT TO UTILIZE WASTE FUEL Savings:
$14,634
Cost:
$50,965
- - $14,634 1,263 - - - - -
-
kWh
$14,634
1,263
MMBtu
-
-
$
-
-
$
06: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$47,532
Cost:
$293,579
$119,828 720,252 $(-15,187) (-2,879) $(-19,951) - $(-37,158) - $119,828
720,252
kWh
$(-15,187)
(-2,879)
MMBtu
$(-19,951)
-
$
$(-37,158)
-
$
07: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$201,027
Cost:
$1,738,526
$201,027 1,208,310 - - - - - - $201,027
1,208,310
kWh
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$278,388
Cost:
$2,090,763
$334,487 2,009,799 $1,010 (-1,480) $(-19,951) - $(-37,158) - $334,487
2,009,799
kWh
$1,010
(-1,480)
MMBtu
$(-19,951)
-
$
$(-37,158)
-
$
TOTAL IMPLEMENTED Savings:
$278,104
Cost:
$2,090,663
$334,203 2,008,095 $1,010 (-1,480) $(-19,951) - $(-37,158) - $334,203
2,008,095
kWh
$1,010
(-1,480)
MMBtu
$(-19,951)
-
$
$(-37,158)
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Natural Gas Personnel Changes Administrative Changes Electricity Usage Natural Gas Personnel Changes Administrative Changes