Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2020 |
Principal Product | In-shell Almonds, Raw Almonds, Almond Oil and Almond Powder |
NAICS | 311911 - Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068 - Salted And Roasted Nuts And Seeds |
Sales | $10,000,000-$50,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 9,000,000 Pounds |
Production Hrs. Annual | 4,480 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $139,741 | 1,347,499 | kWh | $0.10 |
Electricity Demand | $125,510 | 5,628 | kW-months/year | $22.30 |
Natural Gas | $4,017 | 280 | MMBtu | $14.35 |
TOTAL ENERGY COSTS | $269,268 | |||
RECOMMENDED SAVINGS* | $146,492 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $111,131 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $25,284 Cost: - |
- | - | $25,284 | 1,134 | - | - | - | - | - | - |
- - kWh |
$25,284 1,134 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,516 Cost: - |
$4,596 | 44,324 | - | - | - | - | $(-1,080) | - | - | - |
$4,596 44,324 kWh |
- - kW-months/year |
- - MMBtu |
$(-1,080) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $575 Cost: $137 |
$95 | 915 | $480 | 22 | - | - | - | - | - | - |
$95 915 kWh |
$480 22 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $896 Cost: $400 |
$896 | 6,282 | - | - | - | - | - | - | - | - |
$896 6,282 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $2,065 Cost: $1,862 |
- | - | $2,065 | 93 | - | - | - | - | - | - |
- - kWh |
$2,065 93 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $10,077 Cost: $12,392 |
$7,225 | 69,677 | $7,111 | 319 | $(-4,259) | (-297) | - | - | - | - |
$7,225 69,677 kWh |
$7,111 319 kW-months/year |
$(-4,259) (-297) MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,621 Cost: $33,085 |
$6,878 | 66,034 | $5,712 | 256 | - | - | $739 | - | $2,292 | - |
$6,878 66,034 kWh |
$5,712 256 kW-months/year |
- - MMBtu |
$739 - $ |
$2,292 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $88,458 Cost: $451,750 |
$58,025 | 559,550 | $30,433 | 1,365 | - | - | - | - | - | - |
$58,025 559,550 kWh |
$30,433 1,365 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $146,492 Cost: $499,626 |
$77,715 | 746,782 | $71,085 | 3,189 | $(-4,259) | (-297) | $(-341) | - | $2,292 | - | $77,715 746,782 kWh |
$71,085 3,189 kW-months/year |
$(-4,259) (-297) MMBtu |
$(-341) - $ |
$2,292 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $111,131 Cost: $487,234 |
$70,490 | 677,105 | $38,690 | 1,736 | - | - | $(-341) | - | $2,292 | - | $70,490 677,105 kWh |
$38,690 1,736 kW-months/year |
- - MMBtu |
$(-341) - $ |
$2,292 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material |