IAC logo
IAC Assessment: SF0566
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0566
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2021
Principal Product Treated Water
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales $5,000,000-$10,000,000
# of Employees 10
Plant Area (Sq.Ft.) 652,200
Annual Production 1,100,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $422,235 4,114,377 kWh $0.10
Electricity Demand $176,833 5,988 kW-months/year $29.53
TOTAL ENERGY COSTS $630,068
RECOMMENDED SAVINGS* $413,825 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Solid Waste (haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Solid Waste (haz) Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ lb $ $ $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$8,567
Cost:
-
- - $8,129 854 $438 - - - - - - - -
-
kWh
$8,129
854
kW-months/year
$438
-
$
-
-
lb
-
-
$
-
-
$
02: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$72,559
Cost:
$11,960
$54,950 535,418 $17,609 587 - - - - - - - - $54,950
535,418
kWh
$17,609
587
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$126,207
Cost:
$44,180
$95,579 931,300 $30,628 1,020 - - - - - - - - $95,579
931,300
kWh
$30,628
1,020
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$17,474
Cost:
$38,541
$10,018 97,608 $5,435 181 - - - - $1,098 - $923 - $10,018
97,608
kWh
$5,435
181
kW-months/year
-
-
$
-
-
lb
$1,098
-
$
$923
-
$
05: 2.9141 Install Anaerobic Digester Savings:
$189,018
Cost:
$1,222,260
$126,296 1,230,600 $36,972 1,232 - - $25,750 300,000 - - - - $126,296
1,230,600
kWh
$36,972
1,232
kW-months/year
-
-
$
$25,750
300,000
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$413,825
Cost:
$1,316,941
$286,843 2,794,926 $98,773 3,874 $438 - $25,750 300,000 $1,098 - $923 - $286,843
2,794,926
kWh
$98,773
3,874
kW-months/year
$438
-
$
$25,750
300,000
lb
$1,098
-
$
$923
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ lb $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Solid Waste (haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Solid Waste (haz) Personnel Changes Ancillary Material Cost