Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Stevens Institute of Technology |
---|---|
Assessment Year | 1984 |
Principal Product | DAILY NEWSPAPERS |
NAICS | n/a |
SIC | 2711 - Newspapers |
Sales | $1,000,000-$5,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 18,096,000 Pieces |
Production Hrs. Annual | 7,748 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $113,019 | 1,606,096 | kWh | $0.07 |
Natural Gas | $1,933 | 267 | MMBtu | $7.24 |
Fuel Oil #4 | $12,926 | 2,016 | MMBtu | $6.41 |
TOTAL ENERGY COSTS | $127,878 | |||
RECOMMENDED SAVINGS* | $29,351 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,725 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #4 | Administrative Changes | Electricity Usage | Fuel Oil #4 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,031 Cost: $1,461 |
$7,031 | 99,941 | - | - | - | - |
$7,031 99,941 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $1,034 Cost: $130 |
- | - | $1,034 | 162 | - | - |
- - kWh |
$1,034 162 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $4,307 Cost: $590 |
- | - | $4,307 | 675 | - | - |
- - kWh |
$4,307 675 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $5,741 Cost: $1,000 |
$4,516 | 64,185 | $1,225 | 192 | - | - |
$4,516 64,185 kWh |
$1,225 192 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE |
Savings: $2,694 Cost: $50 |
$2,062 | 29,308 | $632 | 99 | - | - |
$2,062 29,308 kWh |
$632 99 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $8,544 Cost: $2,000 |
$227 | 3,224 | - | - | $8,317 | - |
$227 3,224 kWh |
- - MMBtu |
$8,317 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,351 Cost: $5,231 |
$13,836 | 196,658 | $7,198 | 1,128 | $8,317 | - | $13,836 196,658 kWh |
$7,198 1,128 MMBtu |
$8,317 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,725 Cost: $1,511 |
$9,093 | 129,249 | $632 | 99 | - | - | $9,093 129,249 kWh |
$632 99 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #4 | Administrative Changes | Electricity Usage | Fuel Oil #4 | Administrative Changes |