IAC logo
IAC Assessment: ST0011
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Stevens Institute of Technology
Assessment Year 1984
Principal Product METAL SQUEEZE TUBES
NAICS n/a
SIC 3499 - Fabricated Metal Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 65
Plant Area (Sq.Ft.) 0
Annual Production 1,200,000 Pounds
Production Hrs. Annual 2,375
Location (State) NJ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $57,680 545,135 kWh $0.11
Natural Gas $19,811 3,088 MMBtu $6.42
Fuel Oil #2 $13,825 1,820 MMBtu $7.60
TOTAL ENERGY COSTS $91,316
RECOMMENDED SAVINGS* $10,575 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,427
#|Description Savings
Cost
Status Electricity Usage Natural Gas Fuel Oil #2 Electricity Usage Natural Gas Fuel Oil #2
$ kWh $ MMBtu $ MMBtu
01: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$4,259
Cost:
-
- - - - $4,259 574 -
-
kWh
-
-
MMBtu
$4,259
574
MMBtu
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$148
Cost:
$537
- - - - $148 20 -
-
kWh
-
-
MMBtu
$148
20
MMBtu
03: 2.7441 REPLACE BROKEN WINDOWS AND/OR WINDOW SASH Savings:
$1,083
Cost:
$190
- - - - $1,083 146 -
-
kWh
-
-
MMBtu
$1,083
146
MMBtu
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$2,107
Cost:
$2,290
- - - - $2,107 284 -
-
kWh
-
-
MMBtu
$2,107
284
MMBtu
05: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$138
Cost:
-
- - $138 22 - - -
-
kWh
$138
22
MMBtu
-
-
MMBtu
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$93
Cost:
$45
$93 879 - - - - $93
879
kWh
-
-
MMBtu
-
-
MMBtu
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,210
Cost:
$56
$1,210 11,430 - - - - $1,210
11,430
kWh
-
-
MMBtu
-
-
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$869
Cost:
$435
$869 8,206 - - - - $869
8,206
kWh
-
-
MMBtu
-
-
MMBtu
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$668
Cost:
$500
- - - - $668 90 -
-
kWh
-
-
MMBtu
$668
90
MMBtu
TOTAL RECOMMENDED Savings:
$10,575
Cost:
$4,053
$2,172 20,515 $138 22 $8,265 1,114 $2,172
20,515
kWh
$138
22
MMBtu
$8,265
1,114
MMBtu
TOTAL IMPLEMENTED Savings:
$10,427
Cost:
$3,516
$2,172 20,515 $138 22 $8,117 1,094 $2,172
20,515
kWh
$138
22
MMBtu
$8,117
1,094
MMBtu
Savings
Cost
$ kWh $ MMBtu $ MMBtu
Electricity Usage Natural Gas Fuel Oil #2 Electricity Usage Natural Gas Fuel Oil #2