Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Stevens Institute of Technology |
---|---|
Assessment Year | 1986 |
Principal Product | CUSTOMIZED BERYLIUM COPPER |
NAICS | n/a |
SIC | 3495 - Wire Springs |
Sales | $10,000,000-$50,000,000 |
# of Employees | 263 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 200,000 Pieces |
Production Hrs. Annual | 6,675 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $356,018 | 5,025,205 | kWh | $0.07 |
Natural Gas | $11,544 | 2,106 | MMBtu | $5.48 |
Fuel Oil #4 | $40,365 | 7,484 | MMBtu | $5.39 |
TOTAL ENERGY COSTS | $407,927 | |||
RECOMMENDED SAVINGS* | $111,523 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $32,844 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #4 | Electricity Usage | Natural Gas | Fuel Oil #4 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,729 Cost: $90 |
$4,729 | 66,823 | - | - | - | - |
$4,729 66,823 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $698 Cost: $1,000 |
- | - | - | - | $698 | 130 |
- - kWh |
- - MMBtu |
$698 130 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $807 Cost: $537 |
- | - | - | - | $807 | 150 |
- - kWh |
- - MMBtu |
$807 150 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED |
Savings: $1,017 Cost: - |
$1,017 | 14,361 | - | - | - | - |
$1,017 14,361 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,719 Cost: $4,200 |
$2,541 | 35,756 | $(-822) | (-153) | - | - |
$2,541 35,756 kWh |
$(-822) (-153) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $20,785 Cost: $36,000 |
$20,785 | 293,376 | - | - | - | - |
$20,785 293,376 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,345 Cost: $813 |
$4,345 | 61,254 | - | - | - | - |
$4,345 61,254 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $463 Cost: $486 |
$463 | 6,448 | - | - | - | - |
$463 6,448 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $16,026 Cost: $30,000 |
$28,171 | 397,714 | $(-12,145) | (-2,262) | - | - |
$28,171 397,714 kWh |
$(-12,145) (-2,262) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $60,934 Cost: $175,000 |
$90,051 | 1,271,395 | $(-29,117) | (-5,422) | - | - |
$90,051 1,271,395 kWh |
$(-29,117) (-5,422) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $111,523 Cost: $248,126 |
$152,102 | 2,147,127 | $(-42,084) | (-7,837) | $1,505 | 280 | $152,102 2,147,127 kWh |
$(-42,084) (-7,837) MMBtu |
$1,505 280 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $32,844 Cost: $38,926 |
$31,339 | 442,262 | - | - | $1,505 | 280 | $31,339 442,262 kWh |
- - MMBtu |
$1,505 280 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #4 | Electricity Usage | Natural Gas | Fuel Oil #4 |