Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2025 |
Principal Product | sausage |
NAICS | 311611 - Animal (except Poultry) Slaughtering |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $10,000,000-$50,000,000 |
# of Employees | 201 |
Plant Area (Sq.Ft.) | 32,528 |
Annual Production | 12,589,474 Pounds |
Production Hrs. Annual | 5,200 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $46,621 | 2,931,182 | kWh | $0.02 |
Electricity Demand | $59,726 | 8,110 | kW-months/year | $7.36 |
Electricity Fees | $9,682 | - | $ | - |
Natural Gas | $25,662 | 5,152 | MMBtu | $4.98 |
Other Gas | $5,408 | 1 | MMBtu | $5,407.71 |
TOTAL ENERGY COSTS | $147,100 | |||
RECOMMENDED SAVINGS* | $6,625 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,986 Cost: - |
- | - | $2,986 | 406 | - | - | - | - | - | - |
- - kWh |
$2,986 406 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $110 Cost: - |
- | - | - | - | $110 | 22 | - | - | - | - |
- - kWh |
- - kW-months/year |
$110 22 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,993 Cost: $246 |
$106 | 6,642 | $148 | 20 | - | - | $1,739 | - | - | - |
$106 6,642 kWh |
$148 20 kW-months/year |
- - MMBtu |
$1,739 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $404 Cost: $89 |
$184 | 11,475 | $464 | 63 | $(-244) | (-49) | - | - | - | - |
$184 11,475 kWh |
$464 63 kW-months/year |
$(-244) (-49) MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $172 Cost: $69 |
$172 | 10,724 | - | - | - | - | - | - | - | - |
$172 10,724 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $281 Cost: $370 |
- | - | - | - | $281 | 38 | - | - | - | - |
- - kWh |
- - kW-months/year |
$281 38 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $243 Cost: $531 |
$39 | 2,453 | $25 | 3 | - | - | - | - | $179 | - |
$39 2,453 kWh |
$25 3 kW-months/year |
- - MMBtu |
- - $ |
$179 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $436 Cost: $1,102 |
$436 | 27,228 | - | - | - | - | - | - | - | - |
$436 27,228 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $6,625 Cost: $2,407 |
$936 | 58,523 | $3,623 | 492 | $148 | 11 | $1,739 | - | $179 | - | $936 58,523 kWh |
$3,623 492 kW-months/year |
$148 11 MMBtu |
$1,739 - $ |
$179 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost |