Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas, Arlington |
---|---|
Assessment Year | 2001 |
Principal Product | Missile Casing, Ordinance & Alum. For. |
NAICS | n/a |
SIC | 3769 - Space Vehicle Equipment, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 195,000 |
Annual Production | 25,000,000 Tons |
Production Hrs. Annual | 6,448 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $735,046 | 23,235,120 | kWh | $0.03 |
Electricity Demand | $172,995 | 54,401 | kW-months/year | $3.18 |
Electricity Fees | $87,192 | - | $ | - |
Natural Gas | $1,201,382 | 175,233 | MMBtu | $6.86 |
TOTAL ENERGY COSTS | $2,196,615 | |||
RECOMMENDED SAVINGS* | $469,224 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $465,114 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1224 REPLACE BOILER |
Savings: $420,482 Cost: $9,456 |
$(-19,798) | (-464,256) | $(-2,748) | (-864) | $443,028 | 64,417 |
$(-19,798) (-464,256) kWh |
$(-2,748) (-864) kW-months/year |
$443,028 64,417 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4222 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN |
Savings: $15,055 Cost: $600 |
$13,720 | 321,700 | $1,335 | 420 | - | - |
$13,720 321,700 kWh |
$1,335 420 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $13,585 Cost: $2,910 |
$13,585 | 318,580 | - | - | - | - |
$13,585 318,580 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $11,090 Cost: $1,200 |
$11,090 | 260,090 | - | - | - | - |
$11,090 260,090 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2514 COVER OPEN TANKS |
Savings: $2,000 Cost: $3,900 |
$2,000 | 46,857 | - | - | - | - |
$2,000 46,857 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $1,920 Cost: $54 |
$1,920 | 45,075 | - | - | - | - |
$1,920 45,075 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,696 Cost: $225 |
$1,362 | 31,938 | $334 | 105 | - | - |
$1,362 31,938 kWh |
$334 105 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,600 Cost: - |
$1,380 | 32,488 | $220 | 69 | - | - |
$1,380 32,488 kWh |
$220 69 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,032 Cost: $320 |
$1,032 | 24,200 | - | - | - | - |
$1,032 24,200 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7122 DISCONNECT BALLASTS |
Savings: $510 Cost: $982 |
$450 | 10,562 | $60 | 20 | - | - |
$450 10,562 kWh |
$60 20 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $254 Cost: $542 |
$230 | 5,396 | $24 | 7 | - | - |
$230 5,396 kWh |
$24 7 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $469,224 Cost: $20,189 |
$26,971 | 632,630 | $(-775) | (-243) | $443,028 | 64,417 | $26,971 632,630 kWh |
$(-775) (-243) kW-months/year |
$443,028 64,417 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $465,114 Cost: $15,307 |
$23,141 | 542,723 | $(-1,055) | (-332) | $443,028 | 64,417 | $23,141 542,723 kWh |
$(-1,055) (-332) kW-months/year |
$443,028 64,417 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |