Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas, Arlington |
---|---|
Assessment Year | 2004 |
Principal Product | Plastic Products and Industrial Molds |
NAICS | 333511 - Industrial Mold Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 75,000 |
Annual Production | 2,000,000 Pounds |
Production Hrs. Annual | 6,648 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $154,727 | 2,805,000 | kWh | $0.06 |
Electricity Demand | $48,913 | 6,426 | kW-months/year | $7.61 |
Electricity Fees | $155 | - | $ | - |
Natural Gas | $4,785 | 563 | MMBtu | $8.50 |
TOTAL ENERGY COSTS | $237,980 | |||
RECOMMENDED SAVINGS* | $52,019 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,933 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $15,473 Cost: $150 |
- | - | - | - | - | - | $15,473 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$15,473 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $12,900 Cost: $771 |
$12,900 | 274,619 | - | - | - | - | - | - |
$12,900 274,619 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $9,615 Cost: $150 |
$9,615 | 204,050 | - | - | - | - | - | - |
$9,615 204,050 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $6,086 Cost: $2,690 |
$6,086 | 129,153 | - | - | - | - | - | - |
$6,086 129,153 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $2,163 Cost: $2,350 |
$2,163 | 45,892 | - | - | - | - | - | - |
$2,163 45,892 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $1,300 Cost: $50 |
- | - | - | - | $1,300 | 1,300 | - | - |
- - kWh |
- - kW-months/year |
$1,300 1,300 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,288 Cost: - |
$2,388 | 50,692 | $900 | 77 | - | - | - | - |
$2,388 50,692 kWh |
$900 77 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,194 Cost: $1,939 |
$517 | 10,973 | $677 | 58 | - | - | - | - |
$517 10,973 kWh |
$677 58 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $52,019 Cost: $8,100 |
$33,669 | 715,379 | $1,577 | 135 | $1,300 | 1,300 | $15,473 | - | $33,669 715,379 kWh |
$1,577 135 kW-months/year |
$1,300 1,300 Tgal |
$15,473 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,933 Cost: $5,410 |
$27,583 | 586,226 | $1,577 | 135 | $1,300 | 1,300 | $15,473 | - | $27,583 586,226 kWh |
$1,577 135 kW-months/year |
$1,300 1,300 Tgal |
$15,473 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes |