Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas, Arlington |
---|---|
Assessment Year | 2005 |
Principal Product | Filtration and seperation equipment |
NAICS | 333413 - Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3569 - General Industrial Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 400,000 |
Annual Production | 200,000 Pieces |
Production Hrs. Annual | 5,704 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $227,536 | 4,172,410 | kWh | $0.05 |
Electricity Demand | $80,708 | 14,478 | kW-months/year | $5.57 |
Natural Gas | $170,709 | 6,354 | MMBtu | $26.87 |
TOTAL ENERGY COSTS | $483,353 | |||
RECOMMENDED SAVINGS* | $32,494 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $11,425 Cost: - |
$11,425 | 237,600 | - | - | - | - |
$11,425 237,600 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $6,850 Cost: $13,700 |
- | - | $6,850 | 1,310 | - | - |
- - kWh |
$6,850 1,310 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $3,925 Cost: - |
$3,925 | 72,390 | - | - | - | - |
$3,925 72,390 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,880 Cost: $1,080 |
$3,230 | 59,570 | $650 | 125 | - | - |
$3,230 59,570 kWh |
$650 125 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $4,083 Cost: $5,319 |
- | - | - | - | $4,083 | 1,307 |
- - kWh |
- - kW-months/year |
$4,083 1,307 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $1,362 Cost: - |
$1,362 | 25,126 | - | - | - | - |
$1,362 25,126 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $969 Cost: $262 |
$807 | 14,887 | $162 | 31 | - | - |
$807 14,887 kWh |
$162 31 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,494 Cost: $20,361 |
$20,749 | 409,573 | $7,662 | 1,466 | $4,083 | 1,307 | $20,749 409,573 kWh |
$7,662 1,466 kW-months/year |
$4,083 1,307 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal |