IAC Assessment: TN0569
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TN0569
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Tennessee
Assessment Year 1996
Principal Product Plastic Extrusion Molding
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 54
Plant Area (Sq.Ft.) 50,000
Annual Production 5,000,000 Pounds
Production Hrs. Annual 6,732
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $42,340 1,194,607 kWh $0.04
Electricity Demand $25,963 3,134 kW-months/year $8.28
Electricity Fees $1,144 - $ -
Natural Gas $6,907 1,057 MMBtu $6.53
TOTAL ENERGY COSTS $121,150
RECOMMENDED SAVINGS* $32,637 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $318
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production
$ kWh $ kW-months/year $ lb $ $ $ $ $ $ $ $
01: 3.8314 PURCHASE HIGH MATERIALS IN RETURNABLE BULK CONTAINERS Savings:
$18,480
Cost:
-
- - - - $18,480 96,000 - - - - - - - - -
-
kWh
-
-
kW-months/year
$18,480
96,000
lb
-
-
$
-
-
$
-
-
$
-
-
$
02: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$3,578
Cost:
$4,440
$(-500) (-16,706) - - - - $(-5,712) - $(-200) - - - $9,990 - $(-500)
(-16,706)
kWh
-
-
kW-months/year
-
-
lb
$(-5,712)
-
$
$(-200)
-
$
-
-
$
$9,990
-
$
03: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP Savings:
$5,833
Cost:
$17,762
$2,971 99,062 $2,122 208 - - - - - - $740 - - - $2,971
99,062
kWh
$2,122
208
kW-months/year
-
-
lb
-
-
$
-
-
$
$740
-
$
-
-
$
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$4,428
Cost:
$4,000
- - $4,428 432 - - - - - - - - - - -
-
kWh
$4,428
432
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$318
Cost:
$30
$158 5,275 $160 12 - - - - - - - - - - $158
5,275
kWh
$160
12
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$32,637
Cost:
$26,232
$2,629 87,631 $6,710 652 $18,480 96,000 $(-5,712) - $(-200) - $740 - $9,990 - $2,629
87,631
kWh
$6,710
652
kW-months/year
$18,480
96,000
lb
$(-5,712)
-
$
$(-200)
-
$
$740
-
$
$9,990
-
$
TOTAL IMPLEMENTED Savings:
$318
Cost:
$30
$158 5,275 $160 12 - - - - - - - - - - $158
5,275
kWh
$160
12
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost By-product Production