Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1997 |
Principal Product | Automotive interior door panels |
NAICS | n/a |
SIC | 3350 - |
Sales | $50,000,000-$100,000,000 |
# of Employees | 485 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 1,820,000 Pieces |
Production Hrs. Annual | 7,056 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $269,453 | 17,127,491 | kWh | $0.02 |
Electricity Demand | $326,544 | 35,496 | kW-months/year | $9.20 |
Electricity Fees | $23,653 | - | $ | - |
LPG | $53,138 | 7,060 | MMBtu | $7.53 |
TOTAL ENERGY COSTS | $1,807,800 | |||
RECOMMENDED SAVINGS* | $171,730 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $167,060 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | LPG | Solid Waste (non-haz) | Primary Raw Material | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | LPG | Solid Waste (non-haz) | Primary Raw Material | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.1172 REVISE RAW MATERIAL SPECS |
Savings: $134,780 Cost: $10,600 |
- | - | - | - | - | - | - | - | $(-2,700) | 17,200 | $137,480 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$(-2,700) 17,200 lb |
$137,480 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL |
Savings: $19,980 Cost: $8,480 |
- | - | - | - | $(-33,182) | (-7,060) | $53,162 | 7,060 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$(-33,182) (-7,060) MMBtu |
$53,162 7,060 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,900 Cost: $3,800 |
$1,640 | 102,579 | $3,260 | 360 | - | - | - | - | - | - | - | - | - | - |
$1,640 102,579 kWh |
$3,260 360 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $4,800 Cost: - |
- | - | - | - | - | - | - | - | $4,800 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$4,800 - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $2,600 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $2,600 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
$2,600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,320 Cost: $2,800 |
$800 | 49,824 | $1,520 | 168 | - | - | - | - | - | - | - | - | - | - |
$800 49,824 kWh |
$1,520 168 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,000 Cost: $375 |
$1,020 | 63,599 | $980 | 108 | - | - | - | - | - | - | - | - | - | - |
$1,020 63,599 kWh |
$980 108 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $350 Cost: $400 |
$20 | 1,172 | $330 | 36 | - | - | - | - | - | - | - | - | - | - |
$20 1,172 kWh |
$330 36 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $171,730 Cost: $26,455 |
$3,480 | 217,174 | $6,090 | 672 | $(-33,182) | (-7,060) | $53,162 | 7,060 | $2,100 | 17,200 | $137,480 | - | $2,600 | - | $3,480 217,174 kWh |
$6,090 672 kW-months/year |
$(-33,182) (-7,060) MMBtu |
$53,162 7,060 MMBtu |
$2,100 17,200 lb |
$137,480 - $ |
$2,600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $167,060 Cost: $22,880 |
$1,640 | 102,579 | $3,260 | 360 | $(-33,182) | (-7,060) | $53,162 | 7,060 | $2,100 | 17,200 | $137,480 | - | $2,600 | - | $1,640 102,579 kWh |
$3,260 360 kW-months/year |
$(-33,182) (-7,060) MMBtu |
$53,162 7,060 MMBtu |
$2,100 17,200 lb |
$137,480 - $ |
$2,600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | LPG | Solid Waste (non-haz) | Primary Raw Material | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | LPG | Solid Waste (non-haz) | Primary Raw Material | Primary Product |