IAC Assessment: TN0660
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TN0660
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Tennessee
Assessment Year 1999
Principal Product Positive displacement pumps
NAICS n/a
SIC 3561 - Pumps And Pumping Equipment
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 85,000
Annual Production 2,100 Pieces
Production Hrs. Annual 3,060
Location (State) SC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $233,969 6,447,831 kWh $0.04
Electricity Demand $92,622 27,162 kW-months/year $3.41
Electricity Fees $192 - $ -
Natural Gas $75,248 13,360 MMBtu $5.63
TOTAL ENERGY COSTS $419,877
RECOMMENDED SAVINGS* $99,982 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $94,532
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Primary Raw Material Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Other Liquid (non-haz) Primary Raw Material Ancillary Material Cost Primary Product
$ kWh $ kW-months/year $ gal $ $ $ $ $ $
01: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$56,525
Cost:
$880
- - - - - - $56,525 - - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
$56,525
-
$
-
-
$
-
-
$
02: 4.721 INITIATE A PROGRAM TO ACQUIRE ISO CERTIFICATION Savings:
$20,100
Cost:
$50,000
- - - - - - - - - - $20,100 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
$
-
-
$
$20,100
-
$
03: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$9,247
Cost:
$4,700
- - $9,247 2,712 - - - - - - - - -
-
kWh
$9,247
2,712
kW-months/year
-
-
gal
-
-
$
-
-
$
-
-
$
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$5,450
Cost:
-
- - - - - - - - $5,450 - - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
$
$5,450
-
$
-
-
$
05: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE Savings:
$5,360
Cost:
$1,070
$5,360 148,886 - - - - - - - - - - $5,360
148,886
kWh
-
-
kW-months/year
-
-
gal
-
-
$
-
-
$
-
-
$
06: 3.6112 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME Savings:
$3,300
Cost:
$8,200
$(-60) (-2,931) - - $3,360 880 - - - - - - $(-60)
(-2,931)
kWh
-
-
kW-months/year
$3,360
880
gal
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$99,982
Cost:
$64,850
$5,300 145,955 $9,247 2,712 $3,360 880 $56,525 - $5,450 - $20,100 - $5,300
145,955
kWh
$9,247
2,712
kW-months/year
$3,360
880
gal
$56,525
-
$
$5,450
-
$
$20,100
-
$
TOTAL IMPLEMENTED Savings:
$94,532
Cost:
$64,850
$5,300 145,955 $9,247 2,712 $3,360 880 $56,525 - - - $20,100 - $5,300
145,955
kWh
$9,247
2,712
kW-months/year
$3,360
880
gal
$56,525
-
$
-
-
$
$20,100
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ $ $ $ $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Primary Raw Material Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Other Liquid (non-haz) Primary Raw Material Ancillary Material Cost Primary Product