Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas Rio Grande Valley |
---|---|
Assessment Year | 2017 |
Principal Product | Fresh produce (bell peppers, chile peppers, cucumbers, eggplants, greens |
NAICS | 311422 - Specialty Canning |
SIC | 2033 - Canned Fruits And Vegetables |
Sales | $10,000,000-$50,000,000 |
# of Employees | 57 |
Plant Area (Sq.Ft.) | 57,000 |
Annual Production | 44,323 Tons |
Production Hrs. Annual | 2,432 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $135,327 | 1,848,925 | kWh | $0.07 |
Electricity Demand | $18,473 | 4,926 | kW-months/year | $3.75 |
TOTAL ENERGY COSTS | $187,816 | |||
RECOMMENDED SAVINGS* | $50,308 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $40,413 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (non-haz) | Electricity Usage | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $30,725 Cost: $22,000 |
- | - | $30,725 | 82,097 |
- - kWh |
$30,725 82,097 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $6,968 Cost: $500 |
$6,968 | 85,693 | - | - |
$6,968 85,693 kWh |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS |
Savings: $9,895 Cost: $10,000 |
$9,895 | 121,689 | - | - |
$9,895 121,689 kWh |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $187 Cost: $55 |
$187 | 2,300 | - | - |
$187 2,300 kWh |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,329 Cost: $60 |
$1,329 | 16,400 | - | - |
$1,329 16,400 kWh |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $1,204 Cost: - |
$1,204 | 14,867 | - | - |
$1,204 14,867 kWh |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $50,308 Cost: $32,615 |
$19,583 | 240,949 | $30,725 | 82,097 | $19,583 240,949 kWh |
$30,725 82,097 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $40,413 Cost: $22,615 |
$9,688 | 119,260 | $30,725 | 82,097 | $9,688 119,260 kWh |
$30,725 82,097 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (non-haz) | Electricity Usage | Solid Waste (non-haz) |