Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas Rio Grande Valley |
---|---|
Assessment Year | 2020 |
Principal Product | Gas main valves |
NAICS | 332911 - Industrial Valve Manufacturing |
SIC | 3491 - Industrial Valves |
Sales | >$500,000,000 |
# of Employees | 280 |
Plant Area (Sq.Ft.) | 49,937 |
Annual Production | 30,000,000 Units |
Production Hrs. Annual | 4,680 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $102,466 | 1,747,440 | kWh | $0.06 |
Electricity Demand | $56,647 | 5,506 | kW-months/year | $10.29 |
Electricity Fees | $15,273 | - | $ | - |
Natural Gas | $6,612 | 5,863 | MMBtu | $1.13 |
TOTAL ENERGY COSTS | $180,998 | |||
RECOMMENDED SAVINGS* | $30,652 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,623 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $1,078 Cost: - |
- | - | $1,078 | 105 | - | - | - | - |
- - kWh |
$1,078 105 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,125 Cost: $1,000 |
$776 | 13,234 | $349 | 34 | - | - | - | - |
$776 13,234 kWh |
$349 34 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,666 Cost: $10,056 |
$5,975 | 101,970 | $2,691 | 261 | - | - | - | - |
$5,975 101,970 kWh |
$2,691 261 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7212 INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS |
Savings: $204 Cost: $102 |
$140 | 2,396 | $63 | 6 | - | - | - | - |
$140 2,396 kWh |
$63 6 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $11,951 Cost: $15,000 |
- | - | - | - | $11,951 | - | - | - |
- - kWh |
- - kW-months/year |
$11,951 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $7,628 Cost: - |
- | - | - | - | - | - | $7,628 | - |
- - kWh |
- - kW-months/year |
- - $ |
$7,628 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $30,652 Cost: $26,158 |
$6,891 | 117,599 | $4,181 | 406 | $11,951 | - | $7,628 | - | $6,891 117,599 kWh |
$4,181 406 kW-months/year |
$11,951 - $ |
$7,628 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,623 Cost: $11,158 |
$6,891 | 117,599 | $3,103 | 302 | - | - | $7,628 | - | $6,891 117,599 kWh |
$3,103 302 kW-months/year |
- - $ |
$7,628 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost |