Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2016 |
Principal Product | Ceramic Microelectronics |
NAICS | 334419 - Other Electronic Component Manufacturing |
SIC | 3087 - Custom Compound Purchased Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 6,200,000 Pieces |
Production Hrs. Annual | 4,680 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $369,700 | 6,423,600 | kWh | $0.06 |
Electricity Demand | $191,972 | 12,788 | kW-months/year | $15.01 |
Natural Gas | $66,900 | 9,987 | MMBtu | $6.70 |
TOTAL ENERGY COSTS | $728,889 | |||
RECOMMENDED SAVINGS* | $75,451 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $41,941 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $33,510 Cost: $75,000 |
$24,743 | 426,612 | $8,767 | 584 | - | - | - | - | - | - | - | - |
$24,743 426,612 kWh |
$8,767 584 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $30,405 Cost: $88,306 |
$18,285 | 315,263 | $12,120 | 808 | - | - | - | - | - | - | - | - |
$18,285 315,263 kWh |
$12,120 808 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1242 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT |
Savings: $4,033 Cost: $3,600 |
- | - | - | - | $1,000 | 149 | $1,854 | 337 | $1,179 | 336,960 | - | - |
- - kWh |
- - kW-months/year |
$1,000 149 MMBtu |
$1,854 337 Tgal |
$1,179 336,960 gal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1212 OPERATE BOILERS ON HIGH FIRE SETTING |
Savings: $4,000 Cost: $12,000 |
- | - | - | - | $2,000 | 300 | $1,222 | 222 | - | - | $778 | - |
- - kWh |
- - kW-months/year |
$2,000 300 MMBtu |
$1,222 222 Tgal |
- - gal |
$778 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,310 Cost: $1,919 |
$1,556 | 26,800 | - | - | $754 | 92 | - | - | - | - | - | - |
$1,556 26,800 kWh |
- - kW-months/year |
$754 92 MMBtu |
- - Tgal |
- - gal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $883 Cost: $1,500 |
$538 | 9,283 | $345 | 23 | - | - | - | - | - | - | - | - |
$538 9,283 kWh |
$345 23 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $310 Cost: $200 |
$229 | 3,942 | $81 | 5 | - | - | - | - | - | - | - | - |
$229 3,942 kWh |
$81 5 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $75,451 Cost: $182,525 |
$45,351 | 781,900 | $21,313 | 1,420 | $3,754 | 541 | $3,076 | 559 | $1,179 | 336,960 | $778 | - | $45,351 781,900 kWh |
$21,313 1,420 kW-months/year |
$3,754 541 MMBtu |
$3,076 559 Tgal |
$1,179 336,960 gal |
$778 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $41,941 Cost: $107,525 |
$20,608 | 355,288 | $12,546 | 836 | $3,754 | 541 | $3,076 | 559 | $1,179 | 336,960 | $778 | - | $20,608 355,288 kWh |
$12,546 836 kW-months/year |
$3,754 541 MMBtu |
$3,076 559 Tgal |
$1,179 336,960 gal |
$778 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (non-haz) | Water Consumption |