IAC Assessment: TT0264
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TT0264
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Tennessee Technological University
Assessment Year 2022
Principal Product Potable Water
NAICS 221310 - Water Supply and Irrigation Systems
SIC 4941 - Water Supply
Sales $10,000,000-$50,000,000
# of Employees 106
Plant Area (Sq.Ft.) 32,600
Annual Production 4,396,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $649,305 10,225,728 kWh $0.06
Electricity Demand $283,505 22,067 kW-months/year $12.85
TOTAL ENERGY COSTS $932,810
RECOMMENDED SAVINGS* $230,086 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $206,002
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$179,945
Cost:
$100,000
$179,945 2,833,795 - - $179,945
2,833,795
kWh
-
-
kW-months/year
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$26,057
Cost:
$60,000
$20,399 321,253 $5,658 440 $20,399
321,253
kWh
$5,658
440
kW-months/year
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$23,609
Cost:
$36,617
$18,486 291,121 $5,123 399 $18,486
291,121
kWh
$5,123
399
kW-months/year
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$475
Cost:
$700
$475 7,485 - - $475
7,485
kWh
-
-
kW-months/year
TOTAL RECOMMENDED Savings:
$230,086
Cost:
$197,317
$219,305 3,453,654 $10,781 839 $219,305
3,453,654
kWh
$10,781
839
kW-months/year
TOTAL IMPLEMENTED Savings:
$206,002
Cost:
$160,000
$200,344 3,155,048 $5,658 440 $200,344
3,155,048
kWh
$5,658
440
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand