Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Alabama |
---|---|
Assessment Year | 2014 |
Principal Product | lumber |
NAICS | 321113 - Sawmills |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | $10,000,000-$50,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 35,000,000 Units |
Production Hrs. Annual | 2,340 |
Location (State) | AL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $361,129 | 4,887,626 | kWh | $0.07 |
Electricity Demand | $0 | 23,066 | kW-months/year | $0.00 |
Electricity Fees | $26,577 | - | $ | - |
Wood | $115,668 | 53,989 | MMBtu | $2.14 |
TOTAL ENERGY COSTS | $503,374 | |||
RECOMMENDED SAVINGS* | $95,239 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,695 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Wood | Electricity Usage | Electricity Fees | Wood | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,710 Cost: $9,095 |
$8,234 | 111,429 | $476 | - | - | - |
$8,234 111,429 kWh |
$476 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $45,368 Cost: $18,153 |
$42,889 | 580,372 | $2,479 | - | - | - |
$42,889 580,372 kWh |
$2,479 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $10,240 Cost: $3,495 |
- | - | - | - | $10,240 | 4,785 |
- - kWh |
- - $ |
$10,240 4,785 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1113 REDUCE COMBUSTION AIR FLOW TO OPTIMUM |
Savings: $4,096 Cost: $7,500 |
- | - | - | - | $4,096 | 1,914 |
- - kWh |
- - $ |
$4,096 1,914 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $3,455 Cost: $1,870 |
$3,266 | 44,193 | $189 | - | - | - |
$3,266 44,193 kWh |
$189 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,117 Cost: $8,661 |
$2,001 | 27,078 | $116 | - | - | - |
$2,001 27,078 kWh |
$116 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.454 MODIFY STARTUP/SHUTDOWN TIMES |
Savings: $15,087 Cost: - |
- | - | $15,087 | - | - | - |
- - kWh |
$15,087 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $6,166 Cost: - |
- | - | $6,166 | - | - | - |
- - kWh |
$6,166 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $95,239 Cost: $48,774 |
$56,390 | 763,072 | $24,513 | - | $14,336 | 6,699 | $56,390 763,072 kWh |
$24,513 - $ |
$14,336 6,699 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,695 Cost: $5,365 |
$3,266 | 44,193 | $189 | - | $10,240 | 4,785 | $3,266 44,193 kWh |
$189 - $ |
$10,240 4,785 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Wood | Electricity Usage | Electricity Fees | Wood |