Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Alabama |
---|---|
Assessment Year | 2016 |
Principal Product | Aluminum |
NAICS | 331313 - Alumina Refining and Primary Aluminum Production |
SIC | 3334 - Primary Aluminum |
Sales | >$500,000,000 |
# of Employees | 900 |
Plant Area (Sq.Ft.) | 4,356,000 |
Annual Production | 1,000,000,000 Pounds |
Production Hrs. Annual | 8,760 |
Location (State) | AL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $12,968,501 | 406,980,557 | kWh | $0.03 |
Electricity Demand | $11,851,287 | 761,536 | kW-months/year | $15.56 |
Electricity Fees | $239,262 | - | $ | - |
Natural Gas | $21,835,988 | 5,674,754 | MMBtu | $3.85 |
TOTAL ENERGY COSTS | $46,895,038 | |||
RECOMMENDED SAVINGS* | $1,559,281 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $94,634 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $660,652 Cost: $392,000 |
- | - | - | - | $660,652 | 171,598 |
- - kWh |
- - kW-months/year |
$660,652 171,598 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $193,333 Cost: $84,408 |
$111,441 | 3,496,726 | $81,892 | 5,263 | - | - |
$111,441 3,496,726 kWh |
$81,892 5,263 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2514 COVER OPEN TANKS |
Savings: $286,063 Cost: $140,000 |
- | - | - | - | $286,063 | 74,302 |
- - kWh |
- - kW-months/year |
$286,063 74,302 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $12,382 Cost: $2,400 |
$7,107 | 223,005 | $5,275 | 339 | - | - |
$7,107 223,005 kWh |
$5,275 339 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $219,290 Cost: $1,047,803 |
$131,407 | 4,123,233 | $87,883 | 5,648 | - | - |
$131,407 4,123,233 kWh |
$87,883 5,648 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $82,252 Cost: $55 |
$48,269 | 1,514,554 | $33,983 | 2,184 | - | - |
$48,269 1,514,554 kWh |
$33,983 2,184 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $16,391 Cost: $20,000 |
$9,825 | 308,290 | $6,566 | 422 | - | - |
$9,825 308,290 kWh |
$6,566 422 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $88,918 Cost: $2,750 |
$52,134 | 1,639,434 | $36,784 | 2,364 | - | - |
$52,134 1,639,434 kWh |
$36,784 2,364 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,559,281 Cost: $1,689,416 |
$360,183 | 11,305,242 | $252,383 | 16,220 | $946,715 | 245,900 | $360,183 11,305,242 kWh |
$252,383 16,220 kW-months/year |
$946,715 245,900 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $94,634 Cost: $2,455 |
$55,376 | 1,737,559 | $39,258 | 2,523 | - | - | $55,376 1,737,559 kWh |
$39,258 2,523 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |