IAC Assessment: UD0038
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0038
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1982
Principal Product LAWN & GARDEN EQUIPMENT
NAICS n/a
SIC 3524 - Lawn And Garden Equipment
Sales $5,000,000-$10,000,000
# of Employees 91
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 2,100
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $45,095 593,494 kWh $0.08
Natural Gas $39,717 10,854 MMBtu $3.66
Fuel Oil #2 $10,000 1,229 MMBtu $8.14
TOTAL ENERGY COSTS $94,812
RECOMMENDED SAVINGS* $11,787 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,787
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,301
Cost:
$50
$2,301 30,188 - - $2,301
30,188
kWh
-
-
MMBtu
02: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$721
Cost:
-
$721 9,379 - - $721
9,379
kWh
-
-
MMBtu
03: 2.6224 SCHEDULE BAKING TIMES OF SMALL AND LARGE COMPONENTS Savings:
$3,584
Cost:
$1,500
$3,584 24,033 - - $3,584
24,033
kWh
-
-
MMBtu
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,327
Cost:
$300
$1,196 15,826 $131 36 $1,196
15,826
kWh
$131
36
MMBtu
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$3,854
Cost:
$10,000
- - $3,854 1,053 -
-
kWh
$3,854
1,053
MMBtu
TOTAL RECOMMENDED Savings:
$11,787
Cost:
$11,850
$7,802 79,426 $3,985 1,089 $7,802
79,426
kWh
$3,985
1,089
MMBtu
TOTAL IMPLEMENTED Savings:
$11,787
Cost:
$11,850
$7,802 79,426 $3,985 1,089 $7,802
79,426
kWh
$3,985
1,089
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas