Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1983 |
Principal Product | COMMERCIAL PRINTINGS |
NAICS | n/a |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 260 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Units |
Production Hrs. Annual | 6,800 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $256,812 | 5,607,855 | kWh | $0.05 |
Natural Gas | $58,574 | 13,675 | MMBtu | $4.28 |
Other Energy | $75,605 | 8,267 | MMBtu | $9.15 |
TOTAL ENERGY COSTS | $390,991 | |||
RECOMMENDED SAVINGS* | $62,548 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Other Energy | Administrative Changes | Electricity Usage | Natural Gas | Other Energy | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,287 Cost: $562 |
$5,694 | 125,733 | - | - | $(-2,407) | (-197) | - | - |
$5,694 125,733 kWh |
- - MMBtu |
$(-2,407) (-197) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1392 REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE |
Savings: $41,500 Cost: $80,000 |
- | - | $(-59,523) | (-11,023) | $101,023 | 8,267 | - | - |
- - kWh |
$(-59,523) (-11,023) MMBtu |
$101,023 8,267 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $5,692 Cost: - |
$5,692 | - | - | - | - | - | - | - |
$5,692 - kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4157 REPLACE WATER COOLING ON PROCESSES WITH AIR COOLING |
Savings: $4,855 Cost: $17,600 |
$4,855 | 94,959 | - | - | - | - | - | - |
$4,855 94,959 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $4,046 Cost: $33,000 |
$4,046 | 79,132 | - | - | - | - | - | - |
$4,046 79,132 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,168 Cost: $400 |
- | - | - | - | - | - | $3,168 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$3,168 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $62,548 Cost: $131,562 |
$20,287 | 299,824 | $(-59,523) | (-11,023) | $98,616 | 8,070 | $3,168 | - | $20,287 299,824 kWh |
$(-59,523) (-11,023) MMBtu |
$98,616 8,070 MMBtu |
$3,168 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Other Energy | Administrative Changes | Electricity Usage | Natural Gas | Other Energy | Administrative Changes |