IAC Assessment: UD0098
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0098
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1983
Principal Product KNIT GOODS
NAICS n/a
SIC 2254 - Knit Underwear Mills
Sales $10,000,000-$50,000,000
# of Employees 306
Plant Area (Sq.Ft.) 0
Annual Production 200,000 Pieces
Production Hrs. Annual 5,500
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $107,986 2,186,108 kWh $0.05
Natural Gas $369,243 68,731 MMBtu $5.37
TOTAL ENERGY COSTS $477,229
RECOMMENDED SAVINGS* $56,126 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER Savings:
$37,152
Cost:
$36,000
$(-228) (-5,569) $37,380 6,336 $(-228)
(-5,569)
kWh
$37,380
6,336
MMBtu
02: 2.7494 INSTALL STORM WINDOWS AND DOORS Savings:
$9,286
Cost:
$8,000
- - $9,286 1,574 -
-
kWh
$9,286
1,574
MMBtu
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$992
Cost:
$590
$1,083 22,860 $(-91) (-15) $1,083
22,860
kWh
$(-91)
(-15)
MMBtu
04: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$6,313
Cost:
$11,424
- - $6,313 1,070 -
-
kWh
$6,313
1,070
MMBtu
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$2,383
Cost:
-
$2,383 - - - $2,383
-
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$56,126
Cost:
$56,014
$3,238 17,291 $52,888 8,965 $3,238
17,291
kWh
$52,888
8,965
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas