Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1984 |
Principal Product | GRAY IRON CASTINGS |
NAICS | n/a |
SIC | 3321 - Gray And Ductile Iron Foundries |
Sales | $1,000,000-$5,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 2,500 Tons |
Production Hrs. Annual | 1,400 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $53,659 | 400,645 | kWh | $0.13 |
Natural Gas | $12,401 | 2,180 | MMBtu | $5.69 |
Fuel Oil #2 | $12,920 | 1,631 | MMBtu | $7.92 |
Other Energy | $26,640 | 4,063 | MMBtu | $6.56 |
TOTAL ENERGY COSTS | $105,620 | |||
RECOMMENDED SAVINGS* | $7,969 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,969 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7244 REVISE SMOKE CLEANUP FROM OPERATIONS |
Savings: $5,989 Cost: $1,000 |
- | - | - | - | $5,989 | 756 |
- - kWh |
- - MMBtu |
$5,989 756 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,135 Cost: $700 |
$1,135 | 8,206 | - | - | - | - |
$1,135 8,206 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.5194 REDESIGN PROCESS |
Savings: $683 Cost: $2,000 |
- | - | $683 | 124 | - | - |
- - kWh |
$683 124 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $162 Cost: $700 |
- | - | $162 | 30 | - | - |
- - kWh |
$162 30 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $7,969 Cost: $4,400 |
$1,135 | 8,206 | $845 | 154 | $5,989 | 756 | $1,135 8,206 kWh |
$845 154 MMBtu |
$5,989 756 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,969 Cost: $4,400 |
$1,135 | 8,206 | $845 | 154 | $5,989 | 756 | $1,135 8,206 kWh |
$845 154 MMBtu |
$5,989 756 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 |