IAC Assessment: UD0280
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0280
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1989
Principal Product METAL PLATING
NAICS n/a
SIC 3471 - Plating And Polishing
Sales $5,000,000-$10,000,000
# of Employees 110
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 6,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $277,926 4,966,002 kWh $0.06
Natural Gas $168,413 44,430 MMBtu $3.79
TOTAL ENERGY COSTS $446,339
RECOMMENDED SAVINGS* $40,396 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $40,396
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE Savings:
$14,040
Cost:
$14,400
- - $14,040 3,857 - - -
-
kWh
$14,040
3,857
MMBtu
-
-
$
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$3,566
Cost:
$7,000
$3,566 98,769 - - - - $3,566
98,769
kWh
-
-
MMBtu
-
-
$
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$16,696
Cost:
-
$18,568 - - - $(-1,872) - $18,568
-
kWh
-
-
MMBtu
$(-1,872)
-
$
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$4,314
Cost:
-
$4,314 - - - - - $4,314
-
kWh
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$825
Cost:
-
$713 19,050 $(-118) (-32) $230 - $713
19,050
kWh
$(-118)
(-32)
MMBtu
$230
-
$
06: 2.7494 INSTALL STORM WINDOWS AND DOORS Savings:
$955
Cost:
$1,920
- - $955 262 - - -
-
kWh
$955
262
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$40,396
Cost:
$23,320
$27,161 117,819 $14,877 4,087 $(-1,642) - $27,161
117,819
kWh
$14,877
4,087
MMBtu
$(-1,642)
-
$
TOTAL IMPLEMENTED Savings:
$40,396
Cost:
$23,320
$27,161 117,819 $14,877 4,087 $(-1,642) - $27,161
117,819
kWh
$14,877
4,087
MMBtu
$(-1,642)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes