Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1989 |
Principal Product | PRESTRESSED CONCRETE |
NAICS | n/a |
SIC | 3272 - Concrete Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 69 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 5,000 Thousand Feet |
Production Hrs. Annual | 2,200 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $112,857 | 1,549,238 | kWh | $0.07 |
Natural Gas | $95,623 | 23,612 | MMBtu | $4.05 |
Fuel Oil #2 | $11,510 | 2,040 | MMBtu | $5.64 |
TOTAL ENERGY COSTS | $219,990 | |||
RECOMMENDED SAVINGS* | $25,054 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,494 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,196 Cost: $700 |
$1,566 | 40,152 | $(-370) | (-91) | - | - | - | - |
$1,566 40,152 kWh |
$(-370) (-91) MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $3,183 Cost: $2,400 |
$3,183 | 152,989 | - | - | - | - | - | - |
$3,183 152,989 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $6,445 Cost: $400 |
$6,445 | 37,808 | - | - | - | - | - | - |
$6,445 37,808 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $941 Cost: $1,000 |
- | - | $941 | 232 | - | - | - | - |
- - kWh |
$941 232 MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $764 Cost: $1,005 |
$765 | 11,137 | $(-51) | (-12) | - | - | $50 | - |
$765 11,137 kWh |
$(-51) (-12) MMBtu |
- - MMBtu |
$50 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $4,534 Cost: $2,000 |
- | - | $4,343 | 1,070 | $441 | 92 | $(-250) | - |
- - kWh |
$4,343 1,070 MMBtu |
$441 92 MMBtu |
$(-250) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7494 INSTALL STORM WINDOWS AND DOORS |
Savings: $4,775 Cost: $2,300 |
- | - | $4,775 | 1,176 | - | - | - | - |
- - kWh |
$4,775 1,176 MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $3,216 Cost: $600 |
- | - | $3,216 | 792 | - | - | - | - |
- - kWh |
$3,216 792 MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,054 Cost: $10,405 |
$11,959 | 242,086 | $12,854 | 3,167 | $441 | 92 | $(-200) | - | $11,959 242,086 kWh |
$12,854 3,167 MMBtu |
$441 92 MMBtu |
$(-200) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,494 Cost: $3,705 |
$2,331 | 51,289 | $3,922 | 967 | $441 | 92 | $(-200) | - | $2,331 51,289 kWh |
$3,922 967 MMBtu |
$441 92 MMBtu |
$(-200) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Administrative Changes |