IAC Assessment: UD0385
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0385
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1992
Principal Product METAL SHELVING
NAICS n/a
SIC 2542 - Partitions And Fixtures, Except Wood
Sales $10,000,000-$50,000,000
# of Employees 160
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 4,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $145,005 2,545,428 kWh $0.06
Natural Gas $132,318 32,289 MMBtu $4.10
TOTAL ENERGY COSTS $277,323
RECOMMENDED SAVINGS* $67,575 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $60,999
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$38,747
Cost:
$60,000
- - $38,747 - -
-
kWh
$38,747
-
MMBtu
02: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS Savings:
$6,576
Cost:
$18,000
$6,576 - - - $6,576
-
kWh
-
-
MMBtu
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$2,703
Cost:
-
$2,703 - - - $2,703
-
kWh
-
-
MMBtu
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$4,026
Cost:
$3,294
- - $4,026 931 -
-
kWh
$4,026
931
MMBtu
05: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS Savings:
$12,716
Cost:
$3,428
- - $12,716 2,940 -
-
kWh
$12,716
2,940
MMBtu
06: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$2,807
Cost:
$2,200
$1,453 67,995 $1,354 313 $1,453
67,995
kWh
$1,354
313
MMBtu
TOTAL RECOMMENDED Savings:
$67,575
Cost:
$86,922
$10,732 67,995 $56,843 4,184 $10,732
67,995
kWh
$56,843
4,184
MMBtu
TOTAL IMPLEMENTED Savings:
$60,999
Cost:
$68,922
$4,156 67,995 $56,843 4,184 $4,156
67,995
kWh
$56,843
4,184
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas