IAC Assessment: UD0442
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0442
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1994
Principal Product innerspring units
NAICS n/a
SIC 2515 - Mattresses And Bedsprings
Sales $10,000,000-$50,000,000
# of Employees 331
Plant Area (Sq.Ft.) 219,000
Annual Production 1,500,000 Pieces
Production Hrs. Annual 8,400
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $347,485 7,443,435 kWh $0.05
Natural Gas $91,645 16,673 MMBtu $5.50
TOTAL ENERGY COSTS $439,130
RECOMMENDED SAVINGS* $32,047 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $28,712
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Ancillary Material Cost Electricity Usage Natural Gas Administrative Changes Ancillary Material Cost
$ kWh $ MMBtu $ $ $ $
01: 3.7212 IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) Savings:
$3,914
Cost:
-
- - - - - - $3,914 - -
-
kWh
-
-
MMBtu
-
-
$
$3,914
-
$
02: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER Savings:
$3,335
Cost:
-
- - - - $3,335 - - - -
-
kWh
-
-
MMBtu
$3,335
-
$
-
-
$
03: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$12,118
Cost:
$1,000
$11,740 541,032 $(-2,822) (-529) $3,200 - - - $11,740
541,032
kWh
$(-2,822)
(-529)
MMBtu
$3,200
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,818
Cost:
$3,360
$1,818 32,825 - - - - - - $1,818
32,825
kWh
-
-
MMBtu
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,952
Cost:
$6,200
$1,952 89,977 - - - - - - $1,952
89,977
kWh
-
-
MMBtu
-
-
$
-
-
$
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$8,910
Cost:
$10,000
- - $8,910 1,670 - - - - -
-
kWh
$8,910
1,670
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$32,047
Cost:
$20,560
$15,510 663,834 $6,088 1,141 $6,535 - $3,914 - $15,510
663,834
kWh
$6,088
1,141
MMBtu
$6,535
-
$
$3,914
-
$
TOTAL IMPLEMENTED Savings:
$28,712
Cost:
$20,560
$15,510 663,834 $6,088 1,141 $3,200 - $3,914 - $15,510
663,834
kWh
$6,088
1,141
MMBtu
$3,200
-
$
$3,914
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Natural Gas Administrative Changes Ancillary Material Cost Electricity Usage Natural Gas Administrative Changes Ancillary Material Cost