Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1995 |
Principal Product | rubber footwear |
NAICS | n/a |
SIC | 3021 - Rubber And Plastics Footwear |
Sales | $10,000,000-$50,000,000 |
# of Employees | 78 |
Plant Area (Sq.Ft.) | 146,000 |
Annual Production | 4,000,000 Pieces |
Production Hrs. Annual | 7,500 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $253,900 | 4,793,376 | kWh | $0.05 |
Natural Gas | $155,955 | 40,581 | MMBtu | $3.84 |
TOTAL ENERGY COSTS | $409,855 | |||
RECOMMENDED SAVINGS* | $219,819 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $13,500 Cost: $5,000 |
- | - | - | - | - | - | $13,500 | - |
- - kWh |
- - MMBtu |
- - $ |
$13,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $5,945 Cost: - |
$5,070 | 112,544 | - | - | - | - | $875 | - |
$5,070 112,544 kWh |
- - MMBtu |
- - $ |
$875 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $8,535 Cost: $4,300 |
$10,519 | 150,059 | $(-1,984) | (-640) | - | - | - | - |
$10,519 150,059 kWh |
$(-1,984) (-640) MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $8,114 Cost: $8,000 |
$8,114 | 135,111 | - | - | - | - | - | - |
$8,114 135,111 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,440 Cost: $10,410 |
$6,440 | 67,702 | - | - | - | - | - | - |
$6,440 67,702 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,260 Cost: $16,682 |
$10,501 | 202,814 | $(-1,241) | (-400) | - | - | - | - |
$10,501 202,814 kWh |
$(-1,241) (-400) MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.5193 CONVERT FROM BATCH TO CONTINUOUS OPERATION |
Savings: $168,025 Cost: $200,000 |
$18,025 | 271,688 | - | - | $140,000 | - | $10,000 | - |
$18,025 271,688 kWh |
- - MMBtu |
$140,000 - $ |
$10,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $219,819 Cost: $244,392 |
$58,669 | 939,918 | $(-3,225) | (-1,040) | $140,000 | - | $24,375 | - | $58,669 939,918 kWh |
$(-3,225) (-1,040) MMBtu |
$140,000 - $ |
$24,375 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes |