Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1998 |
Principal Product | Quartz Manchining, Grinding, lapping, and polishing |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 48 |
Plant Area (Sq.Ft.) | 25,000 |
Annual Production | 350,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $18,421 | 712,192 | kWh | $0.03 |
Electricity Demand | $24,988 | 1,776 | kW-months/year | $14.07 |
Natural Gas | $7,994 | 1,631 | MMBtu | $4.90 |
TOTAL ENERGY COSTS | $55,046 | |||
RECOMMENDED SAVINGS* | $338,554 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $75,600 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $256,936 Cost: $100,000 |
- | - | - | - | - | - | $256,936 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$256,936 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.2135 EXTEND SOLUTION LIFE WITH FILTERING OR CARBONATE FREEZING |
Savings: $45,731 Cost: $4,000 |
- | - | - | - | - | - | - | - | $(-600) | - | $46,331 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$(-600) - $ |
$46,331 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.2135 EXTEND SOLUTION LIFE WITH FILTERING OR CARBONATE FREEZING |
Savings: $21,625 Cost: $4,000 |
- | - | - | - | $13,230 | - | - | - | $(-600) | - | $8,995 | - |
- - kWh |
- - kW-months/year |
$13,230 - $ |
- - $ |
$(-600) - $ |
$8,995 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.2135 EXTEND SOLUTION LIFE WITH FILTERING OR CARBONATE FREEZING |
Savings: $6,584 Cost: $10,000 |
- | - | - | - | $5,292 | - | - | - | $(-1,800) | - | $3,092 | - |
- - kWh |
- - kW-months/year |
$5,292 - $ |
- - $ |
$(-1,800) - $ |
$3,092 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,018 Cost: $16,558 |
$2,352 | 90,563 | $3,666 | 261 | - | - | - | - | - | - | - | - |
$2,352 90,563 kWh |
$3,666 261 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $1,660 Cost: - |
- | - | $1,660 | 118 | - | - | - | - | - | - | - | - |
- - kWh |
$1,660 118 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $338,554 Cost: $134,558 |
$2,352 | 90,563 | $5,326 | 379 | $18,522 | - | $256,936 | - | $(-3,000) | - | $58,418 | - | $2,352 90,563 kWh |
$5,326 379 kW-months/year |
$18,522 - $ |
$256,936 - $ |
$(-3,000) - $ |
$58,418 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $75,600 Cost: $18,000 |
- | - | $1,660 | 118 | $18,522 | - | - | - | $(-3,000) | - | $58,418 | - | - - kWh |
$1,660 118 kW-months/year |
$18,522 - $ |
- - $ |
$(-3,000) - $ |
$58,418 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Personnel Changes | Primary Raw Material | Ancillary Material Cost | By-product Production |