IAC logo
IAC Assessment: UD0564
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0564
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1999
Principal Product aluminum die castings
NAICS n/a
SIC 3363 - Aluminum Die-castings
Sales $10,000,000-$50,000,000
# of Employees 135
Plant Area (Sq.Ft.) 45,000
Annual Production 5,000,000 Pounds
Production Hrs. Annual 7,344
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $58,165 2,721,278 kWh $0.02
Electricity Demand $91,602 6,492 kW-months/year $14.11
Natural Gas $236,181 70,307 MMBtu $3.36
TOTAL ENERGY COSTS $396,002
RECOMMENDED SAVINGS* $301,743 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $50,275
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ gal $ $ $ $
01: 4.1110 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$220,632
Cost:
$300,000
- - - - - - - - $205,632 - $15,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$205,632
-
$
$15,000
-
$
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$22,972
Cost:
$148
$10,950 527,257 $12,022 852 - - - - - - - - $10,950
527,257
kWh
$12,022
852
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$22,776
Cost:
$49,660
- - - - $22,776 6,699 - - - - - - -
-
kWh
-
-
kW-months/year
$22,776
6,699
MMBtu
-
-
gal
-
-
$
-
-
$
04: 2.2514 COVER OPEN TANKS Savings:
$13,847
Cost:
$2,400
- - - - $13,847 4,073 - - - - - - -
-
kWh
-
-
kW-months/year
$13,847
4,073
MMBtu
-
-
gal
-
-
$
-
-
$
05: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION Savings:
$10,689
Cost:
-
- - $10,689 757 - - - - - - - - -
-
kWh
$10,689
757
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
06: 3.4155 METER WASTE WATER Savings:
$5,686
Cost:
$2,200
- - - - - - $5,686 1,890,327 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$5,686
1,890,327
gal
-
-
$
-
-
$
07: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE Savings:
$2,767
Cost:
$3,375
$478 22,860 $525 37 - - - - $1,764 - - - $478
22,860
kWh
$525
37
kW-months/year
-
-
MMBtu
-
-
gal
$1,764
-
$
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,156
Cost:
$5,096
$1,104 52,462 $1,212 86 - - - - $(-160) - - - $1,104
52,462
kWh
$1,212
86
kW-months/year
-
-
MMBtu
-
-
gal
$(-160)
-
$
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$218
Cost:
$684
$56 2,638 $91 6 - - - - - - $71 - $56
2,638
kWh
$91
6
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
$71
-
$
TOTAL RECOMMENDED Savings:
$301,743
Cost:
$363,563
$12,588 605,217 $24,539 1,738 $36,623 10,772 $5,686 1,890,327 $207,236 - $15,071 - $12,588
605,217
kWh
$24,539
1,738
kW-months/year
$36,623
10,772
MMBtu
$5,686
1,890,327
gal
$207,236
-
$
$15,071
-
$
TOTAL IMPLEMENTED Savings:
$50,275
Cost:
$5,923
$11,428 550,117 $23,236 1,646 $13,847 4,073 - - $1,764 - - - $11,428
550,117
kWh
$23,236
1,646
kW-months/year
$13,847
4,073
MMBtu
-
-
gal
$1,764
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $ $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Administrative Changes