IAC Assessment: UD0598
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0598
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2000
Principal Product Custom bar soap products
NAICS n/a
SIC 2841 - Soap And Other Detergents
Sales $10,000,000-$50,000,000
# of Employees 350
Plant Area (Sq.Ft.) 250,000
Annual Production 8,000,000 Pounds
Production Hrs. Annual 6,732
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $73,274 3,332,063 kWh $0.02
Electricity Demand $170,474 12,168 kW-months/year $14.01
Natural Gas $167,223 50,442 MMBtu $3.32
TOTAL ENERGY COSTS $410,971
RECOMMENDED SAVINGS* $1,279,544 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $37,854
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $ $ $
01: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT Savings:
$1,210,579
Cost:
$375,000
$(-240) (-11,430) $(-941) (-67) - - - - - - $1,211,760 - - - $(-240)
(-11,430)
kWh
$(-941)
(-67)
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
$1,211,760
-
$
-
-
$
02: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$22,073
Cost:
$34,288
$(-3,084) (-146,835) $(-6,052) (-432) - - $31,209 22,025,560 - - - - - - $(-3,084)
(-146,835)
kWh
$(-6,052)
(-432)
kW-months/year
-
-
MMBtu
$31,209
22,025,560
Tgal
-
-
lb
-
-
$
-
-
$
03: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED Savings:
$15,756
Cost:
$18,000
- - - - $9,173 2,763 $4,179 2,766,474 $2,404 24,037 - - - - -
-
kWh
-
-
kW-months/year
$9,173
2,763
MMBtu
$4,179
2,766,474
Tgal
$2,404
24,037
lb
-
-
$
-
-
$
04: 3.8314 PURCHASE HIGH MATERIALS IN RETURNABLE BULK CONTAINERS Savings:
$13,603
Cost:
-
- - - - - - - - $(-3,227) (-71,400) $16,830 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$(-3,227)
(-71,400)
lb
$16,830
-
$
-
-
$
05: 2.8118 CHECK FOR ACCURACY OF UTILITY / POWER METERS Savings:
$9,640
Cost:
-
- - - - - - - - - - - - $9,640 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
$9,640
-
$
06: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE Savings:
$3,333
Cost:
-
- - - - $3,333 1,004 - - - - - - - - -
-
kWh
-
-
kW-months/year
$3,333
1,004
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,752
Cost:
$726
$356 16,999 $1,396 100 - - - - - - - - - - $356
16,999
kWh
$1,396
100
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
08: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER Savings:
$1,720
Cost:
$500
- - - - - - $1,720 1,021,157 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,720
1,021,157
Tgal
-
-
lb
-
-
$
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,088
Cost:
$4,253
$397 18,757 $691 49 - - - - - - - - - - $397
18,757
kWh
$691
49
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$1,279,544
Cost:
$432,767
$(-2,571) (-122,509) $(-4,906) (-350) $12,506 3,767 $37,108 25,813,191 $(-823) (-47,363) $1,228,590 - $9,640 - $(-2,571)
(-122,509)
kWh
$(-4,906)
(-350)
kW-months/year
$12,506
3,767
MMBtu
$37,108
25,813,191
Tgal
$(-823)
(-47,363)
lb
$1,228,590
-
$
$9,640
-
$
TOTAL IMPLEMENTED Savings:
$37,854
Cost:
$39,041
$(-2,687) (-128,078) $(-5,361) (-383) $3,333 1,004 $32,929 23,046,717 - - - - $9,640 - $(-2,687)
(-128,078)
kWh
$(-5,361)
(-383)
kW-months/year
$3,333
1,004
MMBtu
$32,929
23,046,717
Tgal
-
-
lb
-
-
$
$9,640
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Administrative Changes