IAC Assessment: UD0620
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0620
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2001
Principal Product Printed circuit boards
NAICS n/a
SIC 3672 - Printed Circuit Boards
Sales $10,000,000-$50,000,000
# of Employees 120
Plant Area (Sq.Ft.) 86,000
Annual Production 50,000 Pieces
Production Hrs. Annual 6,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $134,587 6,094,600 kWh $0.02
Electricity Demand $159,714 11,400 kW-months/year $14.01
Natural Gas $59,493 10,220 MMBtu $5.82
TOTAL ENERGY COSTS $392,862
RECOMMENDED SAVINGS* $57,465 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,444
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ lb $ $
01: 3.5145 RECOVER AND REUSE SPENT ACID BATHS Savings:
$42,596
Cost:
$85,000
- - - - - - - - $26,796 18,480 $11,550 23,100 $4,250 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$26,796
18,480
gal
$11,550
23,100
lb
$4,250
-
$
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$6,449
Cost:
$300
$1,172 55,800 $1,564 112 $3,713 638 - - - - - - - - $1,172
55,800
kWh
$1,564
112
kW-months/year
$3,713
638
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
03: 3.5145 RECOVER AND REUSE SPENT ACID BATHS Savings:
$2,250
Cost:
-
- - - - - - - - $2,250 450 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$2,250
450
gal
-
-
lb
-
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,850
Cost:
-
$1,420 67,630 $430 31 - - - - - - - - - - $1,420
67,630
kWh
$430
31
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,470
Cost:
$3,648
$630 30,000 $840 60 - - - - - - - - - - $630
30,000
kWh
$840
60
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
06: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$1,218
Cost:
-
$1,218 58,000 - - - - - - - - - - - - $1,218
58,000
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
07: 3.4151 MINIMIZE WATER USAGE Savings:
$876
Cost:
$750
- - - - - - $876 150,368 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$876
150,368
Tgal
-
-
gal
-
-
lb
-
-
$
08: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$756
Cost:
-
$756 36,000 - - - - - - - - - - - - $756
36,000
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$57,465
Cost:
$89,698
$5,196 247,430 $2,834 203 $3,713 638 $876 150,368 $29,046 18,930 $11,550 23,100 $4,250 - $5,196
247,430
kWh
$2,834
203
kW-months/year
$3,713
638
MMBtu
$876
150,368
Tgal
$29,046
18,930
gal
$11,550
23,100
lb
$4,250
-
$
TOTAL IMPLEMENTED Savings:
$3,444
Cost:
$3,648
$2,604 124,000 $840 60 - - - - - - - - - - $2,604
124,000
kWh
$840
60
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ lb $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (haz) Solid Waste (non-haz) Ancillary Material Cost