IAC Assessment: UD0621
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0621
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2001
Principal Product Aerospace Products
NAICS n/a
SIC 3599 - Industrial Machinery, Nec
Sales $10,000,000-$50,000,000
# of Employees 160
Plant Area (Sq.Ft.) 78,000
Annual Production 10,000 Pieces
Production Hrs. Annual 7,344
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $141,913 6,450,600 kWh $0.02
Electricity Demand $160,541 11,928 kW-months/year $13.46
Natural Gas $94,584 16,254 MMBtu $5.82
TOTAL ENERGY COSTS $415,416
RECOMMENDED SAVINGS* $73,943 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $25,863
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Solid Waste (non-haz) Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ gal $ lb $ $
01: 3.5112 REPROCESS SPENT OILS ON SITE FOR RE-USE Savings:
$39,420
Cost:
-
- - - - - - $3,780 10,800 - - $35,640 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,780
10,800
gal
-
-
lb
$35,640
-
$
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$11,768
Cost:
-
$1,082 49,200 - - $10,686 1,836 - - - - - - $1,082
49,200
kWh
-
-
kW-months/year
$10,686
1,836
MMBtu
-
-
gal
-
-
lb
-
-
$
03: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$7,723
Cost:
-
$3,016 137,088 $4,707 336 - - - - - - - - $3,016
137,088
kWh
$4,707
336
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
04: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$7,298
Cost:
$3,000
- - - - - - - - $7,298 62,000 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$7,298
62,000
lb
-
-
$
05: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$5,092
Cost:
$2,000
- - - - - - - - - - $5,092 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
$5,092
-
$
06: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,280
Cost:
$2,460
- - - - $1,280 220 - - - - - - -
-
kWh
-
-
kW-months/year
$1,280
220
MMBtu
-
-
gal
-
-
lb
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$966
Cost:
$2,220
$630 14,688 $336 24 - - - - - - - - $630
14,688
kWh
$336
24
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$396
Cost:
-
$194 8,813 $202 14 - - - - - - - - $194
8,813
kWh
$202
14
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$73,943
Cost:
$9,680
$4,922 209,789 $5,245 374 $11,966 2,056 $3,780 10,800 $7,298 62,000 $40,732 - $4,922
209,789
kWh
$5,245
374
kW-months/year
$11,966
2,056
MMBtu
$3,780
10,800
gal
$7,298
62,000
lb
$40,732
-
$
TOTAL IMPLEMENTED Savings:
$25,863
Cost:
$4,460
$4,098 186,288 $4,707 336 $11,966 2,056 - - - - $5,092 - $4,098
186,288
kWh
$4,707
336
kW-months/year
$11,966
2,056
MMBtu
-
-
gal
-
-
lb
$5,092
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ lb $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Solid Waste (non-haz) Administrative Changes