Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2001 |
Principal Product | Coil handling and press feeding equipment |
NAICS | n/a |
SIC | 3549 - Metalworking Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 170,000 |
Annual Production | 8 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $61,034 | 2,179,800 | kWh | $0.03 |
Electricity Demand | $123,926 | 6,948 | kW-months/year | $17.84 |
Natural Gas | $47,505 | 7,876 | MMBtu | $6.03 |
TOTAL ENERGY COSTS | $232,465 | |||
RECOMMENDED SAVINGS* | $162,150 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $109,991 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $94,812 Cost: $8,000 |
- | - | $94,812 | 3,564 | - | - | - | - |
- - kWh |
$94,812 3,564 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $33,500 Cost: $6,000 |
- | - | - | - | - | - | $33,500 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$33,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $15,075 Cost: - |
- | - | - | - | - | - | $15,075 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$15,075 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $9,915 Cost: - |
$2,576 | 92,000 | $7,339 | 276 | - | - | - | - |
$2,576 92,000 kWh |
$7,339 276 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6222 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS |
Savings: $5,264 Cost: - |
- | - | - | - | $5,264 | 940 | - | - |
- - kWh |
- - kW-months/year |
$5,264 940 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,400 Cost: $1,846 |
$251 | 8,950 | $1,149 | 43 | - | - | - | - |
$251 8,950 kWh |
$1,149 43 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,355 Cost: - |
$1,355 | 48,400 | - | - | - | - | - | - |
$1,355 48,400 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $315 Cost: $435 |
- | - | - | - | $315 | 45 | - | - |
- - kWh |
- - kW-months/year |
$315 45 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $307 Cost: $12 |
$66 | 2,344 | $241 | 12 | - | - | - | - |
$66 2,344 kWh |
$241 12 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $207 Cost: $300 |
$66 | 2,360 | $141 | 7 | - | - | - | - |
$66 2,360 kWh |
$141 7 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $162,150 Cost: $16,593 |
$4,314 | 154,054 | $103,682 | 3,902 | $5,579 | 985 | $48,575 | - | $4,314 154,054 kWh |
$103,682 3,902 kW-months/year |
$5,579 985 MMBtu |
$48,575 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $109,991 Cost: $8,000 |
$2,576 | 92,000 | $102,151 | 3,840 | $5,264 | 940 | - | - | $2,576 92,000 kWh |
$102,151 3,840 kW-months/year |
$5,264 940 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |