Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2004 |
Principal Product | Air and gas compressors |
NAICS | 333912 - Air and Gas Compressor Manufacturing |
SIC | 3563 - Air And Gas Compressors |
Sales | $10,000,000-$50,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 1,211 Pieces |
Production Hrs. Annual | 2,805 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $97,862 | 3,765,538 | kWh | $0.03 |
Electricity Demand | $195,138 | 13,896 | kW-months/year | $14.04 |
Natural Gas | $154,845 | 19,164 | MMBtu | $8.08 |
TOTAL ENERGY COSTS | $471,623 | |||
RECOMMENDED SAVINGS* | $93,260 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $65,965 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $40,625 Cost: - |
- | - | $40,625 | 3,144 | - | - | - | - | - | - |
- - kWh |
$40,625 3,144 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $21,440 Cost: $4,000 |
$1,900 | 350,625 | $19,400 | 1,500 | - | - | $(-860) | - | $1,000 | - |
$1,900 350,625 kWh |
$19,400 1,500 kW-months/year |
- - MMBtu |
$(-860) - $ |
$1,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $9,450 Cost: - |
- | - | - | - | - | - | $9,450 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$9,450 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7131 ADD AREA LIGHTING SWITCHES |
Savings: $5,855 Cost: $1,900 |
$1,820 | 72,930 | $4,035 | 312 | - | - | - | - | - | - |
$1,820 72,930 kWh |
$4,035 312 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $3,880 Cost: - |
- | - | $3,880 | 300 | - | - | - | - | - | - |
- - kWh |
$3,880 300 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $4,540 Cost: - |
$250 | 9,659 | $700 | 54 | $3,590 | 444 | - | - | - | - |
$250 9,659 kWh |
$700 54 kW-months/year |
$3,590 444 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,020 Cost: - |
$3,020 | 116,150 | - | - | - | - | - | - | - | - |
$3,020 116,150 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,970 Cost: $420 |
$950 | 36,465 | $2,020 | 156 | - | - | - | - | - | - |
$950 36,465 kWh |
$2,020 156 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $1,480 Cost: $2,730 |
- | - | - | - | $1,480 | 183 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,480 183 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $93,260 Cost: $9,050 |
$7,940 | 585,829 | $70,660 | 5,466 | $5,070 | 627 | $8,590 | - | $1,000 | - | $7,940 585,829 kWh |
$70,660 5,466 kW-months/year |
$5,070 627 MMBtu |
$8,590 - $ |
$1,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $65,965 Cost: $3,150 |
$4,220 | 162,274 | $47,225 | 3,654 | $5,070 | 627 | $9,450 | - | - | - | $4,220 162,274 kWh |
$47,225 3,654 kW-months/year |
$5,070 627 MMBtu |
$9,450 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |