Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2005 |
Principal Product | Molded Plastics |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 42,000,000 Pounds |
Production Hrs. Annual | 8,736 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $664,871 | 25,668,000 | kWh | $0.03 |
Electricity Demand | $565,500 | 44,232 | kW-months/year | $12.78 |
Natural Gas | $62,800 | 7,700 | MMBtu | $8.16 |
TOTAL ENERGY COSTS | $1,296,271 | |||
RECOMMENDED SAVINGS* | $709,027 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $66,106 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.621 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES |
Savings: $409,000 Cost: $15,000 |
- | - | - | - | - | - | - | - | $409,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$409,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $77,400 Cost: $62,900 |
$41,300 | 1,590,254 | $27,900 | 2,184 | - | - | $8,200 | - | - | - |
$41,300 1,590,254 kWh |
$27,900 2,184 kW-months/year |
- - MMBtu |
$8,200 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.621 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES |
Savings: $64,584 Cost: $200,000 |
- | - | - | - | - | - | - | - | $64,584 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$64,584 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $42,615 Cost: $44,322 |
$25,439 | 978,432 | $17,176 | 1,344 | - | - | - | - | - | - |
$25,439 978,432 kWh |
$17,176 1,344 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $45,734 Cost: $178,576 |
$27,331 | 1,051,200 | $18,403 | 1,440 | - | - | - | - | - | - |
$27,331 1,051,200 kWh |
$18,403 1,440 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7314 REDUCE VENTILATION AIR |
Savings: $37,367 Cost: $19,721 |
- | - | - | - | $37,367 | 4,619 | - | - | - | - |
- - kWh |
- - kW-months/year |
$37,367 4,619 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $19,025 Cost: $13,430 |
$11,357 | 436,800 | $7,668 | 600 | - | - | - | - | - | - |
$11,357 436,800 kWh |
$7,668 600 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $4,300 Cost: $12,500 |
$4,300 | 167,000 | - | - | - | - | - | - | - | - |
$4,300 167,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,805 Cost: $2,598 |
$2,271 | 87,360 | $1,534 | 120 | - | - | - | - | - | - |
$2,271 87,360 kWh |
$1,534 120 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $2,913 Cost: - |
- | - | $2,913 | 228 | - | - | - | - | - | - |
- - kWh |
$2,913 228 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,522 Cost: $3,044 |
$909 | 34,944 | $613 | 48 | - | - | - | - | - | - |
$909 34,944 kWh |
$613 48 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $762 Cost: $362 |
$456 | 17,520 | $306 | 24 | - | - | - | - | - | - |
$456 17,520 kWh |
$306 24 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $709,027 Cost: $552,453 |
$113,363 | 4,363,510 | $76,513 | 5,988 | $37,367 | 4,619 | $8,200 | - | $473,584 | - | $113,363 4,363,510 kWh |
$76,513 5,988 kW-months/year |
$37,367 4,619 MMBtu |
$8,200 - $ |
$473,584 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $66,106 Cost: $203,044 |
$909 | 34,944 | $613 | 48 | - | - | - | - | $64,584 | - | $909 34,944 kWh |
$613 48 kW-months/year |
- - MMBtu |
- - $ |
$64,584 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Primary Product |